BEGIN:VCALENDAR
VERSION:2.0
PRODID:-//CERN//INDICO//EN
BEGIN:VEVENT
SUMMARY:Current state of copper stabilizers and methodology towards calcul
 ating risk
DTSTART;VALUE=DATE-TIME:20110125T165000Z
DTEND;VALUE=DATE-TIME:20110125T171000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-58@cern.ch
DESCRIPTION:Speakers: KORATZINOS\, Mike (CERN)\nThe talk will start by rev
 iewing the landscape: a brief mention of the results of the warm copper st
 abilizer measurements and the results of the splice measurements at cold w
 ill be shown. The preliminary results of the recent RRR measurements will 
 then be presented. Then\, together with the limits presented from talk no.
  2\, the probability of an incident will be presented for beam energies be
 tween 3.5 and 5TeV.  The available methods at our disposal for addressing 
 the limiting factors and operating at a higher energy will then be reviewe
 d:  a complete circuit qualification method coined the Thermal Amplifier c
 an define the maximum safe energy of the LHC in case of a quench next to a
  defective joint. Ways of avoiding magnet quenches\, another critical elem
 ent of the analysis\, for instance by optimizing BLM settings will then be
  shown. Finally\, a proposal of a strategy for running at the highest poss
 ible energy compatible with a pre-defined level of risk will be presented.
  As a case study\, the method will also be applied on the training campaig
 n of sector 56\, where a significant number of quenches at currents above 
 10\,000A were seen with no adverse effects. Were we simply lucky with this
  training campaign?\n\nhttp://indico.cern.ch/contributionDisplay.py?contri
 bId=58&sessionId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=58&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:The LHC RF System: plans for the next long shutdown
DTSTART;VALUE=DATE-TIME:20110125T082000Z
DTEND;VALUE=DATE-TIME:20110125T083500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-30@cern.ch
DESCRIPTION:Speakers: BRUNNER\, Olivier (CERN)\nThe potential limitations 
 for future running of the LHC RF systems are presented. In particular the 
 problems of trips\, hardware failures and limitations encountered during 2
 010 operation period are discussed\, with emphasize on the possible hardwa
 re modifications and upgrades during the next long shutdown. The main tech
 nical challenges as well as the consequences of delaying the shutdown from
  2012 to 2013 are highlighted.\n\nhttp://indico.cern.ch/contributionDispla
 y.py?contribId=30&sessionId=2&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=30&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Consequences of a hypothetical incident for different sectors
DTSTART;VALUE=DATE-TIME:20110125T181000Z
DTEND;VALUE=DATE-TIME:20110125T182500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-54@cern.ch
DESCRIPTION:Speakers: TAVIAN\, Laurent Jean (CERN)\nDuring the 2009 long s
 hutdown\, the LHC machine has been partially consolidated by adding safety
  relief devices in order to better protect the cryostats against large hel
 ium release and consequently to mitigate the risks of collateral damage. A
 fter recalling the present relief valve implementation and other mitigatio
 ns related to the collateral damage\, this paper describes the damage proc
 ess of a hypothetical incident\, presents its consequences for the differe
 nt sectors and for beam energies up to 5 TeV with emphasis on the induced 
 downtime.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=54&ses
 sionId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=54&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Limits for Beam-Induced Damage: Reckless or too Cautious?
DTSTART;VALUE=DATE-TIME:20110126T080000Z
DTEND;VALUE=DATE-TIME:20110126T082000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-42@cern.ch
DESCRIPTION:Speakers: BERTARELLI\, Alessandro (CERN)\nAccidental events im
 plying direct beam impacts on collimators are of the utmost importance as 
 they may lead to serious limitations of the overall LHC Performance. In or
 der to assess damage threshold of components impacted by high energy densi
 ty beams\, advanced numerical simulation methods are under continuous deve
 lopment. Results of analyses carried out on several Phase 1 Collimators ar
 e discussed. In particular\, the number and size of proton bunches leading
  to catastrophic failure of a Tungsten collimator (TCT) are described in d
 etail.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=42&sessio
 nId=4&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=42&sessionId=4&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:R2E relocation and shielding activities
DTSTART;VALUE=DATE-TIME:20110125T084500Z
DTEND;VALUE=DATE-TIME:20110125T090000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-29@cern.ch
DESCRIPTION:Speakers: PERROT\, Anne-Laure ()\nIn the framework of the R2E 
 mitigation project\, relocation and shielding campaigns will be performed 
 during the next long shutdown in parallel in Points 1\, 5\, 7 and 8. About
  15 groups will be involved in these R2E activities with work periods from
  few days to several months. The baseline for these relocations and shield
 ing installations is today defined. The status of the integration studies 
 and their constraints will be discussed aiming for the different teams to 
 be ready for the 2012 shutdown. The impact on the work achievement of a po
 ssible delay of the R2E activities by one year will be presented.\n\nhttp:
 //indico.cern.ch/contributionDisplay.py?contribId=29&sessionId=2&confId=10
 3957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=29&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Discussion
DTSTART;VALUE=DATE-TIME:20110124T110000Z
DTEND;VALUE=DATE-TIME:20110124T113000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-60@cern.ch
DESCRIPTION:Speakers: \nhttp://indico.cern.ch/contributionDisplay.py?contr
 ibId=60&sessionId=0&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=60&sessionId=0&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:What are the consequences of delaying the shutdown from 2012 to 20
 13 for  Radiation Protection?
DTSTART;VALUE=DATE-TIME:20110124T162500Z
DTEND;VALUE=DATE-TIME:20110124T163500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-62@cern.ch
DESCRIPTION:Speakers: ROESLER\, Stefan (CERN)\nThe residual induced radio-
 activity in the LHC underground areas in 2012  will be estimated (assuming
  200 days of high intensity proton operation in 2011). These estimates wil
 l be compared with the levels that would be expected in 2013 (assuming 200
  days of high intensity proton operation in both 2011 and 2012). With thes
 e estimations some consequences of delaying the shutdown from 2012 to 2013
  will be presented.\n\nhttp://indico.cern.ch/contributionDisplay.py?contri
 bId=62&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=62&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Discussion
DTSTART;VALUE=DATE-TIME:20110127T113000Z
DTEND;VALUE=DATE-TIME:20110127T120000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-63@cern.ch
DESCRIPTION:Speakers: \nhttp://indico.cern.ch/contributionDisplay.py?contr
 ibId=63&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=63&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 01 : Review of 2010 Operations
DTSTART;VALUE=DATE-TIME:20110128T073000Z
DTEND;VALUE=DATE-TIME:20110128T074000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-64@cern.ch
DESCRIPTION:Speakers: MEDDAHI\, Malika (CERN)\, PONCE\, Laurette (CERN)\nh
 ttp://indico.cern.ch/contributionDisplay.py?contribId=64&sessionId=9&confI
 d=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=64&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 02 -03 : Shutdown 2012
DTSTART;VALUE=DATE-TIME:20110128T074500Z
DTEND;VALUE=DATE-TIME:20110128T075500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-65@cern.ch
DESCRIPTION:Speakers: BAIRD\, Simon (CERN)\, FORAZ\, Katy (CERN)\nhttp://i
 ndico.cern.ch/contributionDisplay.py?contribId=65&sessionId=9&confId=10395
 7
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=65&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 04 : Beam Energy
DTSTART;VALUE=DATE-TIME:20110128T080000Z
DTEND;VALUE=DATE-TIME:20110128T081000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-66@cern.ch
DESCRIPTION:Speakers: Dr. SIEMKO\, Andrzej (CERN)\, ZANETTI\, Marco (MIT)\
 nhttp://indico.cern.ch/contributionDisplay.py?contribId=66&sessionId=9&con
 fId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=66&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 05 : High Intensity\, Present and Future
DTSTART;VALUE=DATE-TIME:20110128T081500Z
DTEND;VALUE=DATE-TIME:20110128T082500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-67@cern.ch
DESCRIPTION:Speakers: Dr. ASSMANN\, Ralph (CERN)\, Dr. REDAELLI\, Stefano 
 (CERN)\nhttp://indico.cern.ch/contributionDisplay.py?contribId=67&sessionI
 d=9&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=67&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 06 : Machine Protection in 2011 and beyond
DTSTART;VALUE=DATE-TIME:20110128T083000Z
DTEND;VALUE=DATE-TIME:20110128T084000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-68@cern.ch
DESCRIPTION:Speakers: Dr. ZERLAUTH\, Markus (CERN)\, Dr. PAPOTTI\, Giulia 
 (CERN BE/OP)\nhttp://indico.cern.ch/contributionDisplay.py?contribId=68&se
 ssionId=9&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=68&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 07 : Running in 2011 - Luminosity
DTSTART;VALUE=DATE-TIME:20110128T084500Z
DTEND;VALUE=DATE-TIME:20110128T085500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-69@cern.ch
DESCRIPTION:Speakers: LAMONT\, Mike (CERN)\, Miss. KAIN\, Verena (CERN)\nh
 ttp://indico.cern.ch/contributionDisplay.py?contribId=69&sessionId=9&confI
 d=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=69&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Vacuum - Much Ado about Nothing
DTSTART;VALUE=DATE-TIME:20110124T174000Z
DTEND;VALUE=DATE-TIME:20110124T175500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-34@cern.ch
DESCRIPTION:Speakers: Dr. BAGLIN\, Vincent (CERN)\nDuring the next long sh
 utdown\, the majority of the 557 LHC beam and insulation vacuum volumes mu
 st be vented and opened. The activities proposed by the Vacuum\, Surfaces 
 and Coatings Group will be elaborated\, including their implications for o
 ther Groups\, together will an estimation of the extensive VSC workload th
 at is generated by other activities eg splice consolidation\, new collimat
 ors and experimental area upgrades.\n\nhttp://indico.cern.ch/contributionD
 isplay.py?contribId=34&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=34&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Lessons from SPS studies in 2010
DTSTART;VALUE=DATE-TIME:20110128T134500Z
DTEND;VALUE=DATE-TIME:20110128T140500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-24@cern.ch
DESCRIPTION:Speakers: SHAPOSHNIKOVA\, Elena ()\nThe experimental studies d
 one in the SPS in 2010 were devoted  both to a validation of some already 
 proposed upgrades (such as chamber coating) and to uncovering new  limitat
 ions by pushing up the injected bunch intensity.\nThe first results obtain
 ed for higher than nominal intensity LHC beam with 25 ns and 50 ns bunch s
 pacing\, each beam available during only one MD session in the SPS\, will 
 be presented together with results for a single high intensity bunch.\nThe
  limitations encountered during these MD studies will be discussed togethe
 r with other SPS bottlenecks. Possible cures and mitigations will be revis
 ited as well as present achievements.\nAn option for improving the beam st
 ability in the SPS\, opened up again by the successful demonstration  of r
 educing the SPS transition energy\, will also be discussed.\nThe potential
  for delivering bunches with small transverse emittances now and after upg
 rades will be analyzed. An attempt will be made at summarizing the accessi
 ble range of beam parameters (intensity per bunch as a function of distanc
 e between bunches and emittance).\n\nhttp://indico.cern.ch/contributionDis
 play.py?contribId=24&sessionId=8&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=24&sessionId=8&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Electron Clouds in the SPS: progress in the analysis of cures/miti
 gations measures and potential schedule of implementation
DTSTART;VALUE=DATE-TIME:20110128T131500Z
DTEND;VALUE=DATE-TIME:20110128T133500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-25@cern.ch
DESCRIPTION:Speakers: Dr. JIMENEZ\, Jose Miguel (CERN)\nAfter a brief revi
 ew of the studies (simulations and measurements) made so far\, a set of pr
 iorities for new studies will be presented and justified. These proposals 
 will include all studies related to coating techniques\, clearing electrod
 es\, active feedbacks\, together with their related instrumentation.\nThe 
 feasibility\, state-of-the-art\, hard limits and opened questions\, requir
 ed infrastructures\, schedule implications\, phasing feasibility of the pr
 oposed mitigation solutions will be considered in the frame of only the up
 grade of the SPS (i.e. without removing the beampipes from the magnets) an
 d in the frame of combining the SPS upgrade with its required long-term co
 nsolidation (exchange of the magnet beampipes as an alternative).\nA tenta
 tive schedule of milestones in the decision making will be presented and d
 iscussed.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=25&ses
 sionId=8&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=25&sessionId=8&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Alternative / complementary possibilities
DTSTART;VALUE=DATE-TIME:20110128T141500Z
DTEND;VALUE=DATE-TIME:20110128T143500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-26@cern.ch
DESCRIPTION:Speakers: CARLI\, Christian (CERN)\nGeneration of higher brigh
 tness LHC bunch trains in the PS with RF gymnastics different from the pre
 sent scheme has been studied.  With Linac4 and exploiting the beam of all 
 four PSB rings to fill most of the PS circumference allows bringing the PS
  close to the direct space charge limit with one injection.  Batch compres
 sion after acceleration to an appropriate intermediate energy allows incre
 asing the beam brightness at the price of reducing slightly the number of 
 bunches per PS batch. Potential beam characteristics at PS ejection have b
 een estimated\, with and without an increase of the PSB to PS transfer ene
 rgy\, and with a single or a double batch injection. The impact of shorter
  bunch trains on the downstream accelerators has also been analyzed. These
  new schemes are presented together with their expected benefits. The beam
  experiments required to reduce the uncertainties and prepare a well-found
 ed upgrade proposal are described.\n\nhttp://indico.cern.ch/contributionDi
 splay.py?contribId=26&sessionId=8&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=26&sessionId=8&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Work organization for splice consolidation
DTSTART;VALUE=DATE-TIME:20110124T170500Z
DTEND;VALUE=DATE-TIME:20110124T172000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-27@cern.ch
DESCRIPTION:Speakers: BERTINELLI\, Francesco (CERN)\nThe Splices Task Forc
 e has worked in 2010 to prepare the necessary interventions for 7 TeV oper
 ation. The design solution for consolidating the main interconnection spli
 ces is well advanced. The required activities to implement it are describe
 d\, highlighting working assumptions\, missing resources and schedule cons
 iderations.\nProgress has also been made in assessing other splices\, 6 kA
  praying hands and corrector circuits: results and ongoing work are presen
 ted\, highlighting priorities for the remaining work.\n\nhttp://indico.cer
 n.ch/contributionDisplay.py?contribId=27&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=27&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:How can we reduce the "no beam" time?
DTSTART;VALUE=DATE-TIME:20110124T101000Z
DTEND;VALUE=DATE-TIME:20110124T103000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-20@cern.ch
DESCRIPTION:Speakers: Dr. VENTURINI DELSOLARO\, Walter ()\nThe machine ope
 rational efficiency will be analyzed by looking at the downtime statistics
  over the 2010 run. Hardware reliability will be reviewed and possible imp
 rovements considered. Access management\, access recovery\, duration and f
 requency of scheduled technical stops will also be discussed. Finally\, th
 e overhead of switching to ions and back will be briefly addressed.\n\nhtt
 p://indico.cern.ch/contributionDisplay.py?contribId=20&sessionId=0&confId=
 103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=20&sessionId=0&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Performance reach of the injectors in 2011
DTSTART;VALUE=DATE-TIME:20110128T101500Z
DTEND;VALUE=DATE-TIME:20110128T103500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-21@cern.ch
DESCRIPTION:Speakers: STEERENBERG\, Rende (CERN)\nThe characteristics of t
 he various LHC beams have been defined long before the LHC became operatio
 nal. After a year of successful LHC running with the different types of LH
 C beams much experience has been gained in the LHC\, but also in the injec
 tors.\nThis talk will summarise the defined and presently obtained beam ch
 aracteristics of the LHC beams in the injector chain together with a brief
  overview of their production schemes and difficulties.\nFinally an outloo
 k for 2011 will be presented\, indicating the possible characteristics for
  the different LHC beams in the injector chain.\n\nhttp://indico.cern.ch/c
 ontributionDisplay.py?contribId=21&sessionId=8&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=21&sessionId=8&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Possibility of a higher PSB to PS transfer energy
DTSTART;VALUE=DATE-TIME:20110128T104500Z
DTEND;VALUE=DATE-TIME:20110128T110500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-22@cern.ch
DESCRIPTION:Speakers: Dr. HANKE\, Klaus (CERN)\nFollowing the Chamonix 201
 0 workshop a task force has been set up to study the feasibility and the i
 mpact of an energy upgrade of the PS Booster from the present 1.4 GeV to a
 bout 2 GeV. The working group has confirmed the feasibility of such an upg
 rade\, and analysed in detail the impact on the accelerator hardware along
  with a cost estimate and a tentative planning. The outcome of the task fo
 rce will be summarized\, with particular emphasis on the remaining limitat
 ions\, risks and uncertainties.\n\nhttp://indico.cern.ch/contributionDispl
 ay.py?contribId=22&sessionId=8&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=22&sessionId=8&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:PS potential performance with a higher injection energy
DTSTART;VALUE=DATE-TIME:20110128T111500Z
DTEND;VALUE=DATE-TIME:20110128T113500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-23@cern.ch
DESCRIPTION:Speakers: Dr. GILARDONI\, Simone (CERN)\nIn the context of the
  LHC Injectors’ upgrade project\, the PS has to be brought up to- and to
  operate reliably at- the level of performance required by the HL-LHC unti
 l the end of the LHC lifetime. The study has started of the potential bene
 fits of increasing the injection energy. An overview of the impact of this
  upgrade will be presented\, with a preliminary estimate of the beam chara
 cteristics at the SPS entrance and the remaining performance limitations. 
 The necessary hardware modifications will be described\, highlighting the 
 critical systems and the risks. The program for the 2011 machine studies a
 nd hardware interventions for refining these plans will be presented.\n\nh
 ttp://indico.cern.ch/contributionDisplay.py?contribId=23&sessionId=8&confI
 d=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=23&sessionId=8&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Do we really need the LHC luminosity upgrade? Or\, which performan
 ce can we get without an upgrade?
DTSTART;VALUE=DATE-TIME:20110127T160000Z
DTEND;VALUE=DATE-TIME:20110127T162500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-46@cern.ch
DESCRIPTION:Speakers: BRUNING\, Oliver (CERN)\nFrom what we know now\, aft
 er the 1st year of LHC operation\, is an upgrade (with major hardware modi
 fications) required for improved beam performance? Will it remove bottlene
 cks? Will a smart new set of LHC parameters – and LHC Injector parameter
 s - do the job? To what extent?\n\nhttp://indico.cern.ch/contributionDispl
 ay.py?contribId=46&sessionId=7&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=46&sessionId=7&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:HL-LHC: parameter space\, constraints and possible options.
DTSTART;VALUE=DATE-TIME:20110127T170000Z
DTEND;VALUE=DATE-TIME:20110127T172500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-47@cern.ch
DESCRIPTION:Speakers: Dr. ZIMMERMANN\, Frank (AB/ABP)\nWhich are the most 
 promising ingredients to boost the LHC integrated luminosity\, including s
 maller beta*\, higher beam intensity\, crab crossing\, large Piwinski angl
 e\, flat longitudinal profile\, and variations of bunch length\, transvers
 e emittance\, crossing angle\, and bunch spacing? How do the various ingre
 dients conspire or compete? How do they pose different requirements on new
  LHC hardware and on the beams from the injectors?  Which is their relativ
 e importance? What are the proposed roadmap and branching points in the re
 search for a solution?\n\nhttp://indico.cern.ch/contributionDisplay.py?con
 tribId=47&sessionId=7&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=47&sessionId=7&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:RF System: Is It Working Well Enough?
DTSTART;VALUE=DATE-TIME:20110126T103000Z
DTEND;VALUE=DATE-TIME:20110126T105000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-44@cern.ch
DESCRIPTION:Speakers: BAUDRENGHIEN\, Philippe (CERN)\nThe first part will 
 review the RF setting-up and operation in 2010: From the initial RF noise 
 concerns (April)\, to the need for longitudinal blow-up with the nominal b
 unch intensity (May)\, then the problems to fill the machine when increasi
 ng the number of injections  (dump triggered by secondary radiation relate
 d to capture losses).  The statistics on RF fault and their cure will also
  be presented.\nThe second part concentrates on the higher intensity and e
 nergy operation foreseen for 2011. We will discuss the improvements expect
 ed from the Longitudinal damper and the benefits and side-effects from the
  1-Turn feedback .  The issue of surviving a klystron trip during physics 
 will be studied\, using both modeling and observations in 2010. Finally th
 e settings proposed for klystrons and cavities (High Voltage\, cathode cur
 rent and Loaded Q) will be presented.\n\nhttp://indico.cern.ch/contributio
 nDisplay.py?contribId=44&sessionId=4&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=44&sessionId=4&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Collimator Improvements 2011 and Upgrade 2012: What Do We Plan?
DTSTART;VALUE=DATE-TIME:20110126T100000Z
DTEND;VALUE=DATE-TIME:20110126T102000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-45@cern.ch
DESCRIPTION:Speakers: Dr. REDAELLI\, Stefano (CERN)\nThe LHC collimation s
 ystem has provided an outstanding performance during the first year of hig
 h-intensity beam operation. The complete Phase I system was commissioned a
 nd delivered routinely a cleaning performance close to the nominal excepti
 ons with relaxed collimator settings. On the other hand\, the first commis
 sioning experience has also provided first indications of system limitatio
 ns alongside of hints for possible improvements. In particular\, the expec
 ted performance limitations from losses in the cold dispersion suppressors
  (DSs) at either side of the warm cleaning insertions have been confirmed.
  While improvements of the system will already be implemented during the 2
 010 shutdown\, the major performance limitation from the DS require a chan
 ge of the machine layout that will be addresses in the 2012 long shutdown.
  In this papers\, the proposed improvements of the system are presented. T
 he expected gains and the implication of the proposed changes on the syste
 m re-commissioning are discussed.\n\nhttp://indico.cern.ch/contributionDis
 play.py?contribId=45&sessionId=4&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=45&sessionId=4&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Cryomagnets\, Interconnections\, Superconducting Circuits: What to
  do in 2012/13 if you are not consolidating splices ?
DTSTART;VALUE=DATE-TIME:20110124T185500Z
DTEND;VALUE=DATE-TIME:20110124T191000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-28@cern.ch
DESCRIPTION:Speakers: TOCK\, Jean-Philippe (CERN)\nThe interventions affec
 ting the cryomagnets\, the interconnections and/or the superconducting cir
 cuits\, excluding main splices consolidation and QPS interventions will be
  presented. All the tasks not covered in other talks of this session will 
 be detailed\, especially:\nthe replacement of cryomagnets\, \nthe consolid
 ation of the connection cryostats\, \nthe repair of interrupted Y-lines\, 
 \nthe installation of safety pressure relief devices (DN200 & 160)\, \nthe
  consolidation of some SAM helium level gauges\, \nthe use and possible ad
 dition of radioprotection samples\nthe investigations of open issues like 
 high resistance splices and superconducting circuits non-conformities \n\n
 Finally\, the present plan\, work organization and workload for these acti
 vities including DS collimators installation\, interventions on the beam l
 ines and leaks localization and repair\, will be summarized.\n\nhttp://ind
 ico.cern.ch/contributionDisplay.py?contribId=28&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=28&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Radiation to Electronics: Reality or Fata Morgana?
DTSTART;VALUE=DATE-TIME:20110126T083000Z
DTEND;VALUE=DATE-TIME:20110126T085000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-43@cern.ch
DESCRIPTION:Speakers: BRUGGER\, Markus (CERN EN/STI/EET)\nA first year of 
 successful LHC operation has passed reaching about 50pb-1 of integrated lu
 minosity (1‰ of nominal\, 5% of 1fb-1) and more than 1% of peak luminosi
 ty\, as well as a successful ion run. It’s thus time having a first look
  on the observed radiation levels around LHC critical areas and to compare
  them to available simulation results. In spite of the still very low inte
 grated intensities and cumulative luminosities\, we will try revisiting th
 e failure rate predictions by looking at both the observed early failures\
 , as well as the additional results from 2010 CNRAD tests. Upcoming possib
 ly in early 2011\, electron cloud and scrubbing issues and their impact on
  radiation levels will also be briefly discussed. Updated predictions for 
 2011 operation and beyond will be deduced\, on the base of the envisaged L
 HC intensity\, energy and luminosity reach. Starting from these estimates\
 , priorities for short-term improvements and beam tests are discussed\, as
  well as a brief overview of upcoming R2E driven mitigation actions.\n\nht
 tp://indico.cern.ch/contributionDisplay.py?contribId=43&sessionId=4&confId
 =103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=43&sessionId=4&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Which systems (except main circuits) should be commissioned/tested
  for 7TeV operation before the long shutdown?
DTSTART;VALUE=DATE-TIME:20110124T160000Z
DTEND;VALUE=DATE-TIME:20110124T161500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-40@cern.ch
DESCRIPTION:Speakers: Dr. POJER\, Mirko (CERN)\nThe key driver of the long
  2012/13 shutdown is the Consolidation of the 13 kA splices. Once the mach
 ine will be back to operation\, the increase of energy to 7 TeV should be 
 possible. Are all circuits and systems ready for 7 TeV operation? This tal
 k will focus on what else could limit LHC high energy operation and how we
  can know that in advance. A period of dedicated testing at the end of ope
 ration and before the long shutdown could give a precious knowledge on the
  status of the machine.\n\nhttp://indico.cern.ch/contributionDisplay.py?co
 ntribId=40&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=40&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Beam Cleaning and Collimation: Too Bad or Too Good?
DTSTART;VALUE=DATE-TIME:20110126T073000Z
DTEND;VALUE=DATE-TIME:20110126T075000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-41@cern.ch
DESCRIPTION:Speakers: Dr. ASSMANN\, Ralph (CERN)\nThe LHC collimation syst
 em intercepts unavoidable beam losses and absorbs the lost beam power. In 
 particular\, it shields the super-conducting magnets against heating from 
 beam loss. Its performance is characterized by the leakage rate or cleanin
 g inefficiency. The system inefficiency depends on the beam energy\, the b
 eam type (protons or ions)\, the collimator settings and operational imper
 fections. The achieved performance during the first full LHC run is presen
 ted. Operational tolerances and difficulties during the 2010 run are revie
 wed. Setup procedures are described and ways for faster setup discussed. B
 ased on the observed loss rates and magnet quench limits future performanc
 e is extrapolated\, in particular for the achievable store beam energy and
  beta*. Observations and updated limits are compared to previous predictio
 ns. Collimator settings for 2011 are proposed and associated limits and ma
 rgins explained. The impact of higher beam energy is discussed.\n\nhttp://
 indico.cern.ch/contributionDisplay.py?contribId=41&sessionId=4&confId=1039
 57
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=41&sessionId=4&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Experience with MPS during the 2010 run
DTSTART;VALUE=DATE-TIME:20110126T160000Z
DTEND;VALUE=DATE-TIME:20110126T162000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-1@cern.ch
DESCRIPTION:Speakers: Dr. WENNINGER\, Jorg (CERN)\nIn 2010 the LHC stored 
 beam energy was pushed to 25 MJ\, ten times above TEVATRON\, in little ove
 r 6 months. No machine protection issues were recorded\, and the reliabili
 ty of the machine protection system (MPS) did not impact beam operation in
  a significant way. After an initial phase of low intensity beam operation
  that was used among other things for the commissioning of the MPS\, the i
 ntensity was increased in steps of a factor 2 up to 2 MJ. Following a stab
 ility run at 2 MJ\, the intensity was increased in steps of around 3 MJs e
 very few days during train operation. The intensity steps and upcoming MP 
 issues were approved and discussed in the restricted Machine Protection Pa
 nel (MPPr) composed of representatives from the main MP sub-systems. Two r
 eviews of the MPS were organized in 2010\, one internal and one external r
 eview. This presentation will discuss the performance of the MPS\, the exp
 erience from the MPPr and of the intensity increase and the outcomes of th
 e reviews.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=1&ses
 sionId=5&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=1&sessionId=5&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Preparing MPS for 2011 run
DTSTART;VALUE=DATE-TIME:20110126T165000Z
DTEND;VALUE=DATE-TIME:20110126T171000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-3@cern.ch
DESCRIPTION:Speakers: Dr. UYTHOVEN\, Jan (CERN)\nThe expected performance 
 of the Machine Protection System for 2011 is presented. An overview of the
  foreseen modifications to the machine protection system components during
  the Christmas stop and the required time for recommissioning is given. Th
 e possible impact of the MPS on the operational parameters of the LHC\, li
 ke beam intensity\, beta*\, emittance and maximum beam energy\, are discus
 sed.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=3&sessionId
 =5&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=3&sessionId=5&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Can operations put the MPS into an unsafe state?
DTSTART;VALUE=DATE-TIME:20110126T162500Z
DTEND;VALUE=DATE-TIME:20110126T164500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-2@cern.ch
DESCRIPTION:Speakers: PONCE\, Laurette ()\nDuring the 2010 run\, the MPS h
 ave been additionally stressed by the commissioning of operational procedu
 res and systems tests. As requested by the MPS external review committee\,
  human factors have to be further minimized and discipline reinforced when
  increasing the stored beam energies towards and beyond the 2010 target of
  30 MJ. This talk will present a synthesis of the Evian discussion on MPS 
 and human factors\, with an emphasis on the tools and procedures to be put
  in place for the 2011 run in order to ensure the machine safety during st
 andard beam operation and after periods of machine developments or technic
 al stops.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=2&sess
 ionId=5&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=2&sessionId=5&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:What are the issues with injecting unsafe beam into the LHC ?
DTSTART;VALUE=DATE-TIME:20110126T175000Z
DTEND;VALUE=DATE-TIME:20110126T181000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-5@cern.ch
DESCRIPTION:Speakers: Dr. BRACCO\, Chiara (CERN)\nNominal LHC operation fo
 resees to inject four batches of 72 bunches at the time. Injection of up t
 o 32 bunches per batch has been tested in 2010 and possible intensity limi
 tation and machine protection issues have been highlighted\, in view of 20
 11 run. Beam leakage at LHCb and ALICE during injection and qualification 
 of the provided protection are evaluated. Encountered and potential failur
 es of the injection system are presented together with existing and requir
 ed redundancy of the injection interlocks. Possible modifications of injec
 tion procedure and implication for filling schemes  are discussed.\n\nhttp
 ://indico.cern.ch/contributionDisplay.py?contribId=5&sessionId=5&confId=10
 3957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=5&sessionId=5&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Is the BLM system ready to go to higher intensities?
DTSTART;VALUE=DATE-TIME:20110126T172500Z
DTEND;VALUE=DATE-TIME:20110126T174500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-4@cern.ch
DESCRIPTION:Speakers: Dr. SAPINSKI\, Mariusz (CERN/BE-BI)\nThe higher beam
  intensities will enhance the effects of the beam losses observed during 2
 010 run. In particular beam losses due to so called UFOs are discussed\, b
 ut also other beam loss phenomena like luminosity losses\, injection losse
 s and the leakage from the collimation system are considered. The current 
 understanding of the quench limits reflected in the BLM thresholds on the 
 cold magnets is presented. The thresholds for possible increased beam ener
 gy are reviewed.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId
 =4&sessionId=5&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=4&sessionId=5&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:LHC Operation – as viewed from the Experiments
DTSTART;VALUE=DATE-TIME:20110124T073000Z
DTEND;VALUE=DATE-TIME:20110124T075000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-7@cern.ch
DESCRIPTION:Speakers: FERRO-LUZZI\, Massimiliano (CERN)\nThis talk will tr
 y to summarize how the LHC experiments have perceived the 2010 run. A crit
 ical review of LHC operation\, beam conditions and luminosity delivery wil
 l be given\, as well as proposals for improvements.\n\nhttp://indico.cern.
 ch/contributionDisplay.py?contribId=7&sessionId=0&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=7&sessionId=0&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Is there a limitation to the stored beam energy for 2011 and beyon
 d?
DTSTART;VALUE=DATE-TIME:20110126T181500Z
DTEND;VALUE=DATE-TIME:20110126T183500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-6@cern.ch
DESCRIPTION:Speakers: Mr. SCHMIDT\, Rüdiger (CERN)\nThe machine protectio
 n systems have been designed to ultimately operate with beams of a stored 
 energy of 360MJ. This presentation will address if there is an intermediat
 e limit and what upgrades are required to permit operation with 360MJ. A f
 ailure in one of the protection systems (BLM\, BIC\, LBDS\, …) could hav
 e catastrophic consequences for LHC. Considering the operational experienc
 e\, the most critical failure modes are reviewed\, their probability is es
 timated and methods for mitigation are discussed. Ideas for reducing the r
 isk include additional interlocks (DIDT interlock\, abort gap cleaning/mon
 itoring\, fast BLMs\, additional BPMs as HW interlock\, aperture measureme
 nts\,…)\, operational procedures and upgrades of hardware systems. There
  are also examples when the beams should NOT be dumped immediately.\n\nhtt
 p://indico.cern.ch/contributionDisplay.py?contribId=6&sessionId=5&confId=1
 03957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=6&sessionId=5&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Injection – issues and potential solutions
DTSTART;VALUE=DATE-TIME:20110124T083000Z
DTEND;VALUE=DATE-TIME:20110124T084500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-9@cern.ch
DESCRIPTION:Speakers: Miss. KAIN\, Verena (CERN)\nDue to the sensitivity o
 f the LHC beam loss monitor systems combined with low thresholds\, losses 
 at injection became a limiting factor during the filling of the LHC. All p
 arameters\, longitudinal and transverse had to be well controlled not to t
 rigger the beam dump at injection. The cause of these losses will be summa
 rized and typical loss patterns and other diagnostics described. Mitigatio
 n measures together with promising first results will be presented togethe
 r with the plans for 2011. Finally the weak points of the current injectio
 n procedure will be discussed in terms of efficiency and protection\, impr
 ovements for the 2011 run will be proposed.\n\nhttp://indico.cern.ch/contr
 ibutionDisplay.py?contribId=9&sessionId=0&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=9&sessionId=0&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Operational challenges (Feed forward from Evian LHC operation work
 shop)
DTSTART;VALUE=DATE-TIME:20110124T080000Z
DTEND;VALUE=DATE-TIME:20110124T082000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-8@cern.ch
DESCRIPTION:Speakers: LAMONT\, Mike (CERN)\nAn attempt is made to synthesi
 ze the outcomes of the Evian workshop. A list of issues and prioritized ac
 tions will be presented. Among others the following issues will discussed:
  overall operational efficiency and potential improvements\; possible opti
 mization of the operational cycle\; machine configuration and associated c
 ommissioning requirements\; adequacy of LHC operational procedures and too
 ls.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=8&sessionId=
 0&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=8&sessionId=0&c
 onfId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Expectations on Management and Performance Evolution: Lessons from
  Tevatron and Other Colliders.
DTSTART;VALUE=DATE-TIME:20110127T174000Z
DTEND;VALUE=DATE-TIME:20110127T180500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-49@cern.ch
DESCRIPTION:Speakers: Dr. SHILTSEV\, Vladimir (Fermilab)\nThe talk will di
 scuss the luminosity evolution of the Tevatron collider at different stage
 s of the Collider Runs Ia\, Ib and II\, emphasize general dynamics of the 
 process\, analyze planned and delivered luminosity integrals\, discuss the
  expectation management lessons\, and compare with other colliders.\n\nhtt
 p://indico.cern.ch/contributionDisplay.py?contribId=49&sessionId=7&confId=
 103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=49&sessionId=7&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:EL Activities during 2012 Long Shutdown
DTSTART;VALUE=DATE-TIME:20110125T095500Z
DTEND;VALUE=DATE-TIME:20110125T101000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-35@cern.ch
DESCRIPTION:Speakers: DUVAL\, Francois ()\nEN/EL will be leading 3 main LH
 C projects: \n-	R2E (relocation of EL equipment in LHC points 1\, 5\, 7 an
 d 8)\n-	Water cooled cables to be replaced in 3 LHC points\n-	UPS (APC SIL
 CON) to be replaced (circa 80 units)\nEN/EL will be involved in many other
 s. Only a few of them are known today. (Vacuum pump cabling\, RF cables re
 placement\, QPS cabling …..) \nSeveral non LHC projects but directly con
 nected to LHC runs will required a major contribution from EN/EL. Computer
  center\, B513 upgrade and CCC upgrade will be the main ones.\nSeveral EL 
 Consolidation works on the power distribution network are more or less aff
 ecting LHC operations:\n-	Prevessin distribution substation & 3.3kV safety
  network\n-	Upgrade/consolidation of 66kV substation protection system\n-	
 Upgrade of SW (ME59) substation (including 66/18kV trafo)\n-	400kV mainten
 ance on both CERN & RTE sides\nAnd many other tasks\, not connected to LHC
  operations\, will sharply increase the EL turnover for the shutdown..\nPo
 stponing the long shutdown from 2012 to 2013 will mainly:\n-	 increase the
  risk on SPS irradiated cables (no replacement since 2008/2009 campaign) \
 n-	Induce schedule changes on CC\, B513 upgrade project\n-	Postpone for th
 e 3rd time RTE maintenance on Bois-Tollot substation and Genissiat power l
 ine\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=35&sessionId
 =2&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=35&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Experiments' expectations
DTSTART;VALUE=DATE-TIME:20110127T073000Z
DTEND;VALUE=DATE-TIME:20110127T075000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-13@cern.ch
DESCRIPTION:Speakers: FERRO-LUZZI\, Massimiliano (CERN)\nAn overview of th
 e requests from the experiments for 2011 (2012?) will be given. This will 
 include integrated luminosity considerations\, special runs and special be
 am conditions. Based on assumptions of achievable beam parameters\, a prop
 osal for the 2011 physics run scenario will be presented.\n\nhttp://indico
 .cern.ch/contributionDisplay.py?contribId=13&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=13&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Cryogenic systems : which consolidations shall be done in 2012/13 
 ?
DTSTART;VALUE=DATE-TIME:20110124T183000Z
DTEND;VALUE=DATE-TIME:20110124T184500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-38@cern.ch
DESCRIPTION:Speakers: PIROTTE\, Olivier (CERN)\nThe operation of the cryog
 enic systems during the first two years at half of the nominal energy has 
 highlighted a number of required consolidations. The main projects will be
  reviewed with emphasis on safety issues\, LHC downtime risk and cryogenic
  systems performance. Finally their status\, cost\, resources and planning
  will be summarized.\n\nhttp://indico.cern.ch/contributionDisplay.py?contr
 ibId=38&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=38&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:San Luis Street Band & Workshop dinner (les Aiglons)
DTSTART;VALUE=DATE-TIME:20110126T190000Z
DTEND;VALUE=DATE-TIME:20110126T220000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-73@cern.ch
DESCRIPTION:Speakers: \nhttp://indico.cern.ch/contributionDisplay.py?contr
 ibId=73&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=73&confId=10395
 7
END:VEVENT
BEGIN:VEVENT
SUMMARY:Closing remarks
DTSTART;VALUE=DATE-TIME:20110128T145000Z
DTEND;VALUE=DATE-TIME:20110128T150000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-72@cern.ch
DESCRIPTION:Speakers: MYERS\, Steve (CERN)\nhttp://indico.cern.ch/contribu
 tionDisplay.py?contribId=72&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=72&confId=10395
 7
END:VEVENT
BEGIN:VEVENT
SUMMARY:General Discussion
DTSTART;VALUE=DATE-TIME:20110128T091500Z
DTEND;VALUE=DATE-TIME:20110128T094500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-71@cern.ch
DESCRIPTION:Speakers: MYERS\, Steve (CERN)\, Dr. ZIMMERMANN\, Frank (AB/AB
 P)\nhttp://indico.cern.ch/contributionDisplay.py?contribId=71&sessionId=9&
 confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=71&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Summary Session 08 : High Luminosity (HL-LHC)
DTSTART;VALUE=DATE-TIME:20110128T090000Z
DTEND;VALUE=DATE-TIME:20110128T091000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-70@cern.ch
DESCRIPTION:Speakers: Prof. ROSSI\, Lucio (CERN)\, DE MARIA\, Riccardo (CE
 RN)\nhttp://indico.cern.ch/contributionDisplay.py?contribId=70&sessionId=9
 &confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=70&sessionId=9&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Splice Consolidation. What will we do?
DTSTART;VALUE=DATE-TIME:20110124T164000Z
DTEND;VALUE=DATE-TIME:20110124T165500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-59@cern.ch
DESCRIPTION:Speakers: FESSIA\, Paolo (CERN)\nIn the frame of the next long
  shut-down of the LHC\, it is foreseen to intervene on all the 13kA interc
 onnections in order to guarantee the necessary margin and redundancy to pr
 ovide safe LHC operation at 7 TeV. In this talk we will provide an overvie
 w of the development work performed in 2010\, the current technical soluti
 on and validation test results\, and the remaining work to be performed in
  preparation for the long shutdown.\n\nhttp://indico.cern.ch/contributionD
 isplay.py?contribId=59&sessionId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=59&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Pushing the limits - beam
DTSTART;VALUE=DATE-TIME:20110127T080000Z
DTEND;VALUE=DATE-TIME:20110127T082000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-14@cern.ch
DESCRIPTION:Speakers: Dr. METRAL\, Elias (CERN)\nMany collective effects w
 ere observed in 2010\, first when the intensity per bunch was increased an
 d subsequently when the number of bunches was pushed up and the bunch spac
 ing was reduced. After a brief review of the LHC performance during the 20
 10 run\, with a particular emphasis on impedance\, beam-beam and electron 
 cloud issues\, the potential of the LHC for 2011 will be discussed. More s
 pecifically\, the maximum bunch/beam intensity and the maximum beam bright
 ness the LHC should be able to swallow will be compared to what the inject
 ors can provide.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId
 =14&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=14&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Beam observations with different bunch spacing and overall synthes
 is
DTSTART;VALUE=DATE-TIME:20110124T094500Z
DTEND;VALUE=DATE-TIME:20110124T100000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-11@cern.ch
DESCRIPTION:Speakers: ARDUINI\, Gianluigi (CERN)\nMachine studies have bee
 n performed at the end of the 2010 proton run to study the machine perform
 ance with bunch trains with 50 and 75 ns spacing in preparation for the pr
 oton run in 2011.\nThe results of the observations and measurements will b
 e summarized and compared with existing models. Possible running scenarios
  for 2011 will be outlined.\n\nhttp://indico.cern.ch/contributionDisplay.p
 y?contribId=11&sessionId=0&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=11&sessionId=0&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Vacuum and Cryogenics observations for different bunch spacing
DTSTART;VALUE=DATE-TIME:20110124T092000Z
DTEND;VALUE=DATE-TIME:20110124T093500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-10@cern.ch
DESCRIPTION:Speakers: Dr. JIMENEZ\, Jose Miguel (CERN)\nFollowing the obse
 rvations of high pressure rises induced by an electron cloud building up i
 n the LHC beam pipes\, studies were launched with beams with 50 and 75 ns 
 bunch spacing at injection energy and with a ramp to 3.5 TeV (only 50 ns b
 unch spacing).\nThis talk will summarize the observations made on the beam
  vacuum and cryogenic systems for both 50 and 75 ns bunch spacing and with
  a ramp in energy (only 50 ns bunch spacing). Some extrapolations will be 
 presented based on the measurements. Finally\, the decided mitigation solu
 tions and beam parameters to be used for the 2011 run will be reviewed.\n\
 nhttp://indico.cern.ch/contributionDisplay.py?contribId=10&sessionId=0&con
 fId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=10&sessionId=0&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:What do the experiments have planned?
DTSTART;VALUE=DATE-TIME:20110125T104500Z
DTEND;VALUE=DATE-TIME:20110125T110000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-39@cern.ch
DESCRIPTION:Speakers: BALL\, Austin (CERN)\nThe shutdown in 2012-13 is the
  first opportunity since physics operation started for the experiments to 
 conduct comprehensive maintenance. This long shutdown will also be used to
  consolidate and upgrade the experimental apparatus so as to fully exploit
  the expected improvements in LHC performance. This talk will summarise th
 e planned activities in all experiments and attempt to identify areas wher
 e resource conflicts may arise.\n\nhttp://indico.cern.ch/contributionDispl
 ay.py?contribId=39&sessionId=2&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=39&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Optimisation of the nominal cycle
DTSTART;VALUE=DATE-TIME:20110124T104000Z
DTEND;VALUE=DATE-TIME:20110124T105500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-12@cern.ch
DESCRIPTION:Speakers: Dr. REDAELLI\, Stefano (CERN)\nThe energy ramp and t
 he betatron squeeze are critical phases of the LHC operation. During the s
 queeze\, delicate optics manipulations take place when the stored energy i
 s maximum. Ramp and squeeze were commissioned rapidly and smoothly became 
 operational. On the other hand\, for the first commissioning exercise\, th
 e focus was put on machine safety and on operational robustness rather the
 n in efficiency for luminosity production. After having cumulated a full y
 ear of experience and having gained important feedback on the machine beha
 viour and on the operational procedures\, it is now time to address effici
 ency optimization while still respecting safe boundaries. In this paper\, 
 the experience with ramp and squeeze is reviewed\, possible bottlenecks ar
 e identified and paths for improvements of the nominal LHC cycle are addre
 ssed. More complex operation configurations\, like combined ramp and squee
 ze or dynamics squeeze with colliding beams\, are also addressed.\n\nhttp:
 //indico.cern.ch/contributionDisplay.py?contribId=12&sessionId=0&confId=10
 3957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=12&sessionId=0&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Pushing the limits: crossing angles\, aperture and beta*
DTSTART;VALUE=DATE-TIME:20110127T083000Z
DTEND;VALUE=DATE-TIME:20110127T085000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-15@cern.ch
DESCRIPTION:Speakers: HERR\, Werner (CERN)\nFirst experiences with collidi
 ng beams at high intensities and small emittances have been collected duri
 ng the 2010 LHC run. These will be critically examined and serve as input 
 to define strategies for operation with more bunches and higher luminositi
 es in 2011. The proposed strategies include running scenarios for proton o
 peration in ALICE and LHCb.\n\nhttp://indico.cern.ch/contributionDisplay.p
 y?contribId=15&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=15&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Breaching the Phase I optics limitations for the HL-LHC
DTSTART;VALUE=DATE-TIME:20110127T163000Z
DTEND;VALUE=DATE-TIME:20110127T165500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-48@cern.ch
DESCRIPTION:Speakers: FARTOUKH\, Stephane (CERN)\nPerformance goal of the 
 HL-LHC (5E34 for the “running” luminosity and 10E34 “potentially ava
 ilable” to reach it).\nNew optics concepts for the HL-LHC (short reminde
 r of the Phase I optics limitations\, description of the new scheme\, pote
 ntial in terms of beta* and beta* aspect ratio and weak points).\nFollowin
 g this specific path\, what is still missing and the most likely additiona
 l ingredients needed to reach the goal and build margins? What can be test
 ed now in the machine?\n\nhttp://indico.cern.ch/contributionDisplay.py?con
 tribId=48&sessionId=7&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=48&sessionId=7&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Luminosity calibration
DTSTART;VALUE=DATE-TIME:20110127T100000Z
DTEND;VALUE=DATE-TIME:20110127T102000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-17@cern.ch
DESCRIPTION:Speakers: WHITE\, Simon Mathieu (Universite de Paris-Sud (Pari
 s XI))\nThe experiments do not only require high collision rates and integ
 rated luminosity\, but also an absolute normalization of the observed cros
 s sections. This normalization can be derived from theoretical predictions
  or the determination of the absolute luminosity. During the 2010 proton r
 un\, the Van Der Meer scan method was used to provide a first measurement 
 of the absolute luminosity from machine parameters. Based on the outcome o
 f the Lumi Days workshop\, future requirements\, prospects and alternative
  methods (vertex\, high beta) will be summarized. \nImplications on machin
 e operation and protection will be discussed.\n\nhttp://indico.cern.ch/con
 tributionDisplay.py?contribId=17&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=17&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Luminosity analysis
DTSTART;VALUE=DATE-TIME:20110127T093000Z
DTEND;VALUE=DATE-TIME:20110127T095000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-16@cern.ch
DESCRIPTION:Speakers: Dr. PAPOTTI\, Giulia (CERN BE/OP)\nThe first year of
  LHC operation was very successful regarding the peak and integrated lumin
 osity targets\, but the luminosity lifetime could probably have been bette
 r. For this reason\, the luminosity evolution during physics fills is stud
 ied and correlated to single beam lifetimes and emittance growth in order 
 to try and understand possible causes of luminosity lifetime decrease\, e.
 g. IBS\, beam-beam related phenomena\, electron-cloud and possibly the “
 hump”.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=16&sess
 ionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=16&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Operational schedule 2011 & potential performance
DTSTART;VALUE=DATE-TIME:20110127T110000Z
DTEND;VALUE=DATE-TIME:20110127T112000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-19@cern.ch
DESCRIPTION:Speakers: MEDDAHI\, Malika (CERN)\nThe assumed LHC beam parame
 ters for 2011 are summarised. The overview of the 2011 schedule is present
 ed and including hardware commissioning\, beam re-commissioning\, re-valid
 ation\, scrubbing\, technical stops\, MD\, ions and special physics run re
 quests. A strategy for stepping up in intensity is proposed and potential 
 issues are described together with possible actions.  Finally\, the potent
 ial peak and integrated luminosity are given.\n\nhttp://indico.cern.ch/con
 tributionDisplay.py?contribId=19&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=19&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Kickers and dumps
DTSTART;VALUE=DATE-TIME:20110125T075500Z
DTEND;VALUE=DATE-TIME:20110125T081000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-32@cern.ch
DESCRIPTION:Speakers: MERTENS\, Volker (CERN)\nPlanned major hardware inte
 rventions include the completion of the staged dilution kicker system in p
 oint 6 (installation of 2 last tanks and associated generators)\, replacem
 ent of the extraction protection elements TCDQ (for performance reasons) a
 nd possibly the replacement of 2 injection kickers. The reliability overha
 ul program for the extraction kicker generators will be completed\, and nu
 merous improvements of electronics and controls of the various systems be 
 carried out\, followed by a thorough test and re-qualification program.\n\
 nhttp://indico.cern.ch/contributionDisplay.py?contribId=32&sessionId=2&con
 fId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=32&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:QPS Activities
DTSTART;VALUE=DATE-TIME:20110125T073000Z
DTEND;VALUE=DATE-TIME:20110125T074500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-31@cern.ch
DESCRIPTION:Speakers: DAHLERUP-PETERSEN\, Knud (CERN)\nThe long shutdown a
 ctivities of the Circuit Protection section form integrated parts of the m
 edium- and long term plan for the consolidation and upgrade of LHC detecto
 r and extraction equipment which is required for maintaining and adapting 
 the complex and safety-critical QPS systems. Although every coming TS shal
 l be efficiently used to advance with these works\, a major part of the ta
 sks\, defined in five project packages\, will need to be implemented durin
 g the shutdown. The packages are: nQPS/BS extension to the SAM’s\, the H
 DS upgrade\, a EE consolidation plan \, general and specific firmware upgr
 ades and a R2E mitigation and replacement program\, representing an estima
 ted total of 55-60 man-months.\n\nhttp://indico.cern.ch/contributionDispla
 y.py?contribId=31&sessionId=2&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=31&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Radiation Protection: How (radio)active are we going to be?
DTSTART;VALUE=DATE-TIME:20110126T093000Z
DTEND;VALUE=DATE-TIME:20110126T095000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-56@cern.ch
DESCRIPTION:Speakers: ROESLER\, Stefan (CERN)\nOperation in 2010 has cause
 d the first components to become radioactive.  An overview of the present 
 residual dose rates around the machine is given and compared to results of
  activation studies. It shows that measurable activation is presently limi
 ted to a few components only\, such as collimators and absorbers. The  pr
 ocedures to be applied for maintenance and repair work in the tunnel and/o
 r workshops reflects the low radiological risk. However\, the comparison t
 o calculated residual dose rates also confirms results of studies and adds
  confidence in predictions for operation in 2011/12. The latter are given 
 assuming operation at 4.5TeV with up to 100 MJ stored beam energy. At the 
 same time\, predictions by pure simulation have limitations which are outl
 ined. In order to overcome them\, assessments combined with measurements a
 re planned and will be summarized. \nFinally\, the implications of the env
 isaged operational scenarios for 2011/12 on maintenance and consolidation 
 work as well as on the validity of compensatory measures are detailed.\n\n
 http://indico.cern.ch/contributionDisplay.py?contribId=56&sessionId=4&conf
 Id=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=56&sessionId=4&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Update on calculations of max. excess resistance allowed as a func
 tion of energy for the case of prompt/semi-prompt/adjacent quenches
DTSTART;VALUE=DATE-TIME:20110125T162500Z
DTEND;VALUE=DATE-TIME:20110125T164500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-51@cern.ch
DESCRIPTION:Speakers: VERWEIJ\, Arjan (CERN)\nOperating at 3.5 TeV with de
 fective 13 kA joints is based on twofold safety: 1) it is extremely unlike
 ly that a magnet quench will propagate to the interconnect\, and even if t
 his occurs\, 2) it is extremely unlikely that the joint will burn through\
 , assuming the measured distribution of defective joints. Above 3.5 TeV\, 
 the currents become sufficiently large to burn a defective joint\, and for
  safety one therefore has to rely on non-quenching the joints. In this pre
 sentation I will focus on the possibility of thermal-electrical quench pro
 pagation through the bus from a quenching magnet to the interconnect. Simu
 lations will be supported by quench propagation measurements recently perf
 ormed in SM18.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=5
 1&sessionId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=51&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Access and Alarm Safety Systems - Activities for the 2012/2013 Lon
 g Shutdown
DTSTART;VALUE=DATE-TIME:20110125T102000Z
DTEND;VALUE=DATE-TIME:20110125T103500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-36@cern.ch
DESCRIPTION:Speakers: GRAU\, Silvia (CERN)\nThis paper presents the 2012/2
 013 long shutdown activities for the access\, emergency evacuation\, gas a
 nd fire detection systems. First\, an overview of the required minimal ann
 ual maintenance and tests is presented\, including the first feedback from
  the 9 weeks of the technical stop. Second\, planned upgrades\, new instal
 lations and consolidation activities\, such as the R2E relocations and sys
 tems improvements\, are discussed. For all these activities\, the required
  resources are estimated\, the constraints on other groups are listed\, th
 e associated risks analyzed and time estimation provided. The evaluation o
 f the required resources takes into consideration the activities in the in
 jector chain during the long shutdown.\n\nhttp://indico.cern.ch/contributi
 onDisplay.py?contribId=36&sessionId=2&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=36&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:What needs to be done to reach beam energy above 3.5 TeV? Commissi
 oning of essential magnet powering and machine protection systems.
DTSTART;VALUE=DATE-TIME:20110125T174000Z
DTEND;VALUE=DATE-TIME:20110125T180500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-53@cern.ch
DESCRIPTION:Speakers: Dr. CATALAN LASHERAS\, Nuria (CERN)\nAfter the initi
 al plans in 2007 to run the LHC at 7 TeV\, a number of unexpected events\,
  and the extended knowledge of the machine that came after them\, have con
 vinced us to gradually reduce the beam energy to the current 3.5 TeV. As a
  consequence of this\, some circuits have been commissioned to different e
 nergy levels.  Some systems\, as the quench protection system\, are worki
 ng at a reduced level of accuracy based on less demanding conditions. Non-
 conformities that were unacceptable for higher energy have no consequences
  at the current energy and are thus accepted. In this talk\, we will revie
 w the current status of commissioning of all the circuits and estimate the
  time and effort necessary to make all circuits operational at higher ener
 gies. All existing nonconformities that need to be solved before increasin
 g the energy will be reviewed and their impact in terms of machine safety 
 and schedule will be assessed.   The talk will try to outline a stepped 
 energy increase compatible with the already planned maintenance periods an
 d balanced between physics and commissioning time.\n\nhttp://indico.cern.c
 h/contributionDisplay.py?contribId=53&sessionId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=53&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Implications of increased beam energy on QPS system\, EE time cons
 tants\, PC
DTSTART;VALUE=DATE-TIME:20110125T171500Z
DTEND;VALUE=DATE-TIME:20110125T173000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-52@cern.ch
DESCRIPTION:Speakers: STECKERT\, Jens ()\nThe operational limits given by 
 the present configuration of the LHC Quench Protection and Energy Extracti
 on Systems will be presented and the necessary modifications to operate wi
 th beam energies of 4\, 4.5 and 5 TeV will be explained. The presentation 
 will not only focus on changes to the hardware such as the installation of
  snubber capacitors for the energy extraction systems but as well on chang
 es of detection settings e.g. for the symmetric quench detection systems. 
 The necessity to increase the fast discharges time constants of the main c
 ircuits will be discussed. Finally the impact and status of eventual syste
 m non-conformities will be addressed.\n\nhttp://indico.cern.ch/contributio
 nDisplay.py?contribId=52&sessionId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=52&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Installing collimators in the next long shut-down: plans\, status 
 and challenges
DTSTART;VALUE=DATE-TIME:20110124T180500Z
DTEND;VALUE=DATE-TIME:20110124T182000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-33@cern.ch
DESCRIPTION:Speakers: PARMA\, Vittorio (CERN)\nThe first part of the colli
 mation upgrade plan features the installation of 4 collimators in the 2 DS
  of point 3\, in addition to the upgrade of the existing collimation syste
 m. \nWhat makes this upgrade so special is that for the first time collima
 tors will be placed within the continuous cryostat of the LHC sectors. For
  this purpose\, 16 main dipoles and 8 main quadrupoles will have to be dis
 connected and displaced by about 4.5 m\, as well as the 2 electrical feedb
 oxes (DFBAs) on either side of the DS\, in order to create the space requi
 red for installing the additional collimators. The collimators themselves\
 , although remaining of the warm type\, feature a design substantially dif
 ferent from the others\, mainly imposed by tight space constraints. These 
 collimator modules will have to be complemented by a special bypass cryost
 at whose function is to preserve the continuity of the technical systems a
 long the arcs (magnet powering\, cryogenics and insulation vacuum)\, while
  providing cold to warm transitions to the beam tubes where the collimator
 s are placed.  \nThe status of this collimation upgrade project will be pr
 esented\, with special emphasis to the collimation in the DS of point 3\; 
 design & integration studies in this point\, as well as the status of the 
 design and manufacturing of all the associated new equipment (DS collimato
 rs\, Short Connection Cryostats\, and new cryogenic extensions to the QRL)
  will be outlined. An overall plan of the surface and tunnel preparation a
 ctivities\, in the perspective of a 2012 shut-down implementation\, is dis
 cussed.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=33&sessi
 onId=1&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=33&sessionId=1&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Operational consequences of running at a higher energies
DTSTART;VALUE=DATE-TIME:20110125T183000Z
DTEND;VALUE=DATE-TIME:20110125T184500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-55@cern.ch
DESCRIPTION:Speakers: LAMONT\, Mike (CERN)\nThe operational overheads of m
 oving above 3.5 TeV are examined. This examination will look at the cost o
 f performing such a move at the start\, or during\, the 2011 run. The impa
 ct of operation with beams above 3.5 TeV on machine protection systems is 
 briefly reviewed and any potential limitations are enumerated. Finally the
  possible benefits of increasing the beam energy on the luminosity are dis
 cussed.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=55&sessi
 onId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=55&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:CV
DTSTART;VALUE=DATE-TIME:20110125T093000Z
DTEND;VALUE=DATE-TIME:20110125T094500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-37@cern.ch
DESCRIPTION:Speakers: DELEVAL\, Serge (CERN)\nThe presentation gives an ov
 erview of the major projects and work foreseen to be performed during the 
 long shutdown on cooling and ventilation plants. Several projects are need
 ed according to the experience of the last years\, in particular the modif
 ications in the water cooling circuits presently in overflow. Some other p
 rojects are linked to the CV consolidation plan. Finally\, most of the wor
 k shall be done to respond to several requests: SR buildings air condition
 ing\, the need to be able to clean and maintain the LHC cooling towers wit
 hout a complete stop of cooling circuits\, the upgrade of the air conditio
 ning of the CCC rack room cooling etc. For all these activities \, the aut
 hor will detail  constraints and the impact on the schedule and on the ope
 ration of the plants that will however need to run for the major part of t
 he shutdown. The consequence of having the long shutdown in 2013 will be a
 lso covered.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=37&
 sessionId=2&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=37&sessionId=2&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Heavy Ions  in 2011 and beyond
DTSTART;VALUE=DATE-TIME:20110127T103000Z
DTEND;VALUE=DATE-TIME:20110127T105000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-18@cern.ch
DESCRIPTION:Speakers: Dr. JOWETT\, John (CERN)\nThe LHC's first heavy ion 
 run set - and tested - the operational pattern for 2011 and later years: a
  rapid commissioning strategy intended to ensure delivery of integrated lu
 minosity despite the risks associated with the short time-frame.  It also 
 gave us hard data to test our understanding of the beam physics that will 
 limit performance.  \nThe 2010 experience is fed into the commissioning pl
 an\, parameter choices and projected performance for 2011.    \nThe prospe
 cts for future stages of the LHC ion program\, Pb-Pb collisions at higher 
 energy and luminosity\, hybrid collisions and other species\, depend criti
 cally on the scheduling of certain hardware upgrades.\n\nhttp://indico.cer
 n.ch/contributionDisplay.py?contribId=18&sessionId=6&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=18&sessionId=6&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:How much Physics benefits from running at higher energies?
DTSTART;VALUE=DATE-TIME:20110125T160000Z
DTEND;VALUE=DATE-TIME:20110125T162000Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-57@cern.ch
DESCRIPTION:Speakers: MURRAY\, Bill (Particle Physics-Rutherford Appleton 
 Laboratory-STFC - Science &)\nIn 2010 the LHC experiments accomplished stu
 nning physics results collecting collision data at the record center of ma
 ss energy of 7 TeV. Such energy is though still a factor two below the des
 ign value of the LHC. Higher beam energy will be beneficial for the physic
 s program of the experiments. The discovery potentials for the main physic
 s objectives will be discussed as a function of center of mass energy (7\,
  8\, and 10 TeV) and integrated luminosity.  The experimental implications
  of running at higher energies and instantaneous luminosities will also be
  presented.\n\nhttp://indico.cern.ch/contributionDisplay.py?contribId=57&s
 essionId=3&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=57&sessionId=3&
 confId=103957
END:VEVENT
BEGIN:VEVENT
SUMMARY:Alice and LHCb in the HL-LHC era.
DTSTART;VALUE=DATE-TIME:20110127T181000Z
DTEND;VALUE=DATE-TIME:20110127T183500Z
DTSTAMP;VALUE=DATE-TIME:20130523T051031Z
UID:indico-contribution-103957-50@cern.ch
DESCRIPTION:Speakers: BERTOLUCCI\, Sergio (CERN)\nSo far all the upgrade s
 chemes have been studied assuming only two general\npurpose detectors\, AT
 LAS and CMS\, operating. Will Alice and LHCb run in HL-LHC time? When and 
 what process to decide it? What are the beam parameters they want to explo
 it and the hardware changes they need in case of an upgrade?\n\nhttp://ind
 ico.cern.ch/contributionDisplay.py?contribId=50&sessionId=7&confId=103957
LOCATION:Chamonix
URL:http://indico.cern.ch/contributionDisplay.py?contribId=50&sessionId=7&
 confId=103957
END:VEVENT
END:VCALENDAR
