13-14 December 2012
FNAL
US/Central timezone
- laurie.hemery@cern.ch
Support
Charge:
-
Review fabrication challenges for the three compact cavities and the present test results
-
Review present conceptual ideas of the two-cavity cryostat including the tuning mechanisms, Helium vessel, shielding, thermal and mechanical analysis, RF system, controls, alignment, instrumentation and integration. Its future adaptation towards the final LHC system should be addressed.
-
Review the timeline for fabrication of the two cavity cryostat and respective systems for the SPS tests and the related prototyping effort.
Starts 13 Dec 2012 08:45
Ends 14 Dec 2012 12:30
US/Central
FNAL
Hermitage Room, Industrial Center Building, 2 East
Batavia, IL
* The workshop is by invitation only. If you would like to participate you are requested to write to the organizers.
For administrative matters, please contact :
- Laurie Hemery, laurie.hemery@cern.ch
Event calendar file
Share this page
Social networks
Calendaring