MEETING GOALS:
- to review specifications and technical choices + to set deadlines for decision on pending questions,
- to define the precise contribution of each partner (deliverables and planning) and the interactions between partners (names of persons in charge, exchange of information/hardware, planning of meetings, …),
- to propose how to demonstrate 25 MV/m (Beta=1) and 19 MV/m (Beta =0.65) before mid-2011
- to list untreated subjects and collect suggestions for addressing them,
- to organize the collaboration (Constitution?),
- to define the dates of the main meetings until end of 2009.
Starts 11 Dec 2008 09:00
Ends 12 Dec 2008 22:05
Europe/Zurich
CERN
AT Auditorium
- Garoby, Roland
WORKINGS GROUPS:
Each participant is asked to register to one or more working group(s).
The mandate of the working groups is to fulfill the meeting goals on a subset of subjects
WG 1: High power RF equipement (RF distrib., amplitude/phase modulators, circulators, loads...)
WG 2: Cavity design (Geometric beta, high power coupler, HOM damper/coupler, tuner...) and construction (Manufacturers, processing facilities, low power RF tests...)
WG 3: Cryomodule and integration (Desing, construction, assembly...)
WG 4: Beam dynamics and loss management (Collective effects, H- stripping, collimation...)