Outline of key beam parameters for the 3.5 TeV run and possible increase in energy (transverse and longitudinal). Potential machine performance. Recall any optics issues and constraints.
Presented by Dr. Massimo GIOVANNOZZI on 20 Jan 2010 at 14:30
Cunning plan for continued commissioning: ramp to 3.5 TeV, squeeze, collisions etc. Prerequisites for going beyond the safe beam limit and approach to increasing the intensity. Schedule for 2010.
Presented by Mike LAMONT on 20 Jan 2010 at 15:00
The Beam Interlock System (BIS) and Safe Machine Parameters (SMP) system are central to the protection of the Large Hadron Collider (LHC) machine. The BIS has been critical for the safe operation of LHC from the first day of operation. It has been installed and commissioned, only minor enhancements are required in order to accommodate all future LHC machine protection requirements. At reduced in ... More
Presented by Dr. Benjamin TODD on 20 Jan 2010 at 09:00
The performance of the beam dumping systems and the abort gap cleaning are reviewed in the context of the general machine protection system. Details of the commissioning experience and setting up, encountered equipment problems, the experience with and status of the eXternal Post Operational Checks (XPOC) and the importance of operational procedures are presented for the beam dumping system. The b ... More
Presented by Dr. Jan UYTHOVEN on 20 Jan 2010 at 09:35
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Mariusz SAPINSKI
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Dr. Christos ZAMANTZAS on 19 Jan 2010 at 14:45
The LHC collimation system has been used for beam cleaning and passive machine protection this year for the first time. The hardware commissioning tests carried out in preparation for operations with beam are presented. Setup procedure towards nominal injection settings is analyzed together with reproducibility and total beam time spent for collimator setup. Locations of beam losses are reviewed a ... More
Presented by Chiara BRACCO on 20 Jan 2010 at 09:15
Presented by Steve MYERS on 20 Jan 2010 at 15:50
Feedback from operational experience- What can be improved?
on 20 Jan 2010 at 12:35
More feedback from operational experience- What can be improved?
on 20 Jan 2010 at 10:30
Feedback from operational experience- What can be improved?
on 19 Jan 2010 at 18:15
some keywords: Improving operational efficiency: sequencing, procedures, training, RBAC, testing
Presented by Dr. Reyes ALEMANY FERNANDEZ on 20 Jan 2010 at 11:35
Results will be shown from the low-intensity beam commissioning of first, the moveable injection protection devices in the SPS to LHC transfer lines and downstream of the LHC injection kicker and second, the LHC dump protection elements in IR6. The implications of these results and a commissioning status report with the further planning will be addressed.
Presented by Wolfgang BARTMANN on 20 Jan 2010 at 09:50
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Malika MEDDAHI on 19 Jan 2010 at 12:05
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Werner HERR on 19 Jan 2010 at 11:45
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Rogelio TOMAS on 19 Jan 2010 at 10:45
- Experimental conditions - Integration of experiment magnets - Ramp strategy for spectrometers - Experience with the handshake - Requests, suggestions?
Presented by Massimiliano FERRO-LUZZI on 19 Jan 2010 at 17:55
Presented by Simon Mathieu WHITE on 19 Jan 2010 at 15:35
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Dr. Ezio TODESCO
Presented by Kajetan FUCHSBERGER on 19 Jan 2010 at 14:00
Performance, measurements vs. expectations, problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Dr. Jorg WENNINGER on 20 Jan 2010 at 10:10
Presented by Thibaut LEFEVRE on 19 Jan 2010 at 15:15
- Performance, observations, problems encountered - Losses and transmission: estrapolation for higher intensities? - Feed-forward vs. feedback: orbit, tune, chroma - Setting incorporation for various systems: tune, chroma, ... RF, collimators - Is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Walter VENTURINI DELSOLARO on 19 Jan 2010 at 16:30
Expectations for 2010 in terms of integrated luminosity and energy. Physics potential given this. Requirements in terms of beam intensity, beam size and bunch configuration. Specific requests for special physics running conditions". Technical stop and likely maintenance requirements through the year.
Presented by Massimiliano FERRO-LUZZI on 20 Jan 2010 at 14:00
- Results from first operation, news for 2010. - Performance, measurements vs. expectations (improvements of online model) - Strategy to bring up luminosity performance - Optimized behaviour vs energy and beta* -> How to handle this in LSA - Problems encountered, is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Werner HERR on 19 Jan 2010 at 17:15
- Performance, observations, problems encountered - Review optics requirements for 2010 in all points - Commissioning base-line and possible issues - Settings of protection devices - Is related software sufficient, necessary improvements, appropriate for 3.5TeV running?
Presented by Dr. Stefano REDAELLI on 19 Jan 2010 at 16:55
Performance of tune, chromaticity and coupling measurement system (BBQ and PLL). Status of feedbacks. Observations of unexpected features in tune spectra (8 kHz, modulation, "the hump").
Presented by Ralph STEINHAGEN, Marek GASIOR on 19 Jan 2010 at 14:20
What was observed in the tune spectra at 450 GeV? The hump, excitation of the tune spectra, lifetime issues.
Presented by Marek GASIOR
- Revise estimates and requirements for operation at higher energies - Model for decay and snap-back - LSA implementation is adequate? - Additional measurement program to update the model
Presented by Dr. Ezio TODESCO on 19 Jan 2010 at 17:35
some keywords: Improving rigor: procedures, checks, releases, testing, RBAC..
Presented by Dr. Brennan GODDARD on 20 Jan 2010 at 11:15
Presented by Paul COLLIER on 20 Jan 2010 at 15:30