Minutes of SPL cavity Working Group meeting on 24.1.2011
Participants:
CERN: R. Calaga, S. Cakatroni, O. Capatina, E. Chiaveri, F. Gerigk, M. Schuh, W. Weingarten.
(no video connection)
 
The proposed agenda was
 
As follow-up, one of the main points is related due the late delivery of Nb for cavity manufacturing by Plansee, delayed by about 6 months. Ofelia has investigated other suppliers and the best options time/money/quality weighed is still to remain with Plansee. This may have an impact on the overall planning of the final cryomodule delivery. At the same time, it may give an opportunity to redesign the helium tank using s.steel (following discussions with CEA during the collaboration meeting). The feasibility of this change will be investigated.
 
Next meeting will be on 7.3.2011
 