GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
***** TO BE UPDATED DURING NEXT MEETING ******
User Reports / Overview :
----------------------------------CO2 Tue 16.4 : strange behaviour of CO2. (drop of CO2 for a few seconds) -> checked with David and no problems was detected from the supply side. Anyhow the investigation is still ongoing.
Bunker Temperature : 1 degree drift. Linked to the the cooling water maintenance - to be finished end of THIS week. -> normal condition from Monday 06th MayALICE : Done ! Gas battery moved out of the EHN1
ATLAS - sTGC : 2 QS1 tested and sent already to bldg.180. 1 QS1 and 1 QS3 to be tested during the week. Today QS3 will be tested and on Monday QS1 will be installed and tested on TUE 14th. After this no other chambers ready to be tested at GIF++. New batch expected in 2 weeks.
ATLAS-MM : LM1-M3 tested and removed on Tuesday 07th afternoon and swapped with SM2-M5 as planned. SM2-M5 to be tested and swapped with LM1-M4 next week.
Universal trolley to arrive mid May. Tentative to be placed in current CMS-DT location. To be check the cabling and the gas piping.
EP-DT1: Fine. Radiating.
EP-DT2 : Measurement ongoing. Preparing for long ageing test. For today 2h filter scan from 22000 to 2.2 with 2 access (one before starting and one in the middle of the measurements period)
EcoGas - HFO bottle delivered and changed. Will last ≈ 18days. Starting stability run. Thus, for this type of test the filter settings upstream will stay to 22 (for one week) after every source scans or special tests.
CMS-RPC : Trolley for testing the electronics in order to launch the mass production to be installed next week on Wed (T.b.c). ISEC visit requested. Source scan for 2h filter settings 6.9
Gas flow needs to be checked, as we are on the limit. Shared with ATLAS-RPC. Gas flow reduced a bit. To be discussed with EP-DT-FS.CMS-GEM 1&2 : 2 is Happy, some problem one GEM 1 (crate outside was failing) - will be fixed with arrival of new chamber. Some delays.
ATLAS-RPC : BIS installed yesterday after CMS-DT chambers removed. Access (30min) needed today in order to check the setup, because there was not enough time yesterday.
CMS-DT MB 1&2 : Removed yesterday and installed on the area between GIF++ and CMS-ECAL. Still the cabling to remove. It will be scheduled for the next Wednesdays
LHCb :New position to be checked.
CMS-CSC: 2h source OFF today after CMS-RPC scan
==========================================================
Weekly Planning : UPSTREAM
Default filter settings : 22 for one week (then going back to 2.2)
Thursday (today): ATLAS-MM 2h scan 10-2.2 started at 9.40am
EP-DT2 14h-16h 22000-2.2 including one short access between
ATLAS-sTGC : 1h scan before EP-DT2
CMS-RPC 2h at 6.9 starting 16h-18h
Friday :
Saturday :
Sunday :
Monday : ATLAS -sTGC : Monday morning access to take out QS3 and install QS1
Tuesday : ATLAS-MM (morning) 4-5h scan, 1h each from 10-1 attenuation ATLAS-sTGC: QS1 to be tested 1h source OFF-ON attenuation 1
Wednesday:
Thursday : ATLAS -MM (morning) 4-5h scan, 1h each from 10-1 attenuation
-------------------------------------------------------------------------------------------------------
Weekly Planning : DOWNSTREAM
Default filter settings : 1
Thursday (today) : ATLAS-RPC Access for 30 minutes today at 13h30. CMS-CSC 2h source OFF after CMS-RPC is over with the scan
Friday :
Saturday :
Sunday :
Monday :
Tuesday :
Wednesday:
-------------------------------------------------------------------------------------------------------
Access Requests :
Thursday:
- 09:35 → 09:40
- 09:40 → 09:50
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Cleaning of DCS and installation of UPS : to be scheduled.
Ongoing Projects :
=============Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only-
Bunker Extension Project 10m
News about the ongoing bunker extension
-
Cosmic Trigger 10m
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2019 !
-
AOB 5m
Issue with ligth. Button near access door should enable the light for additional 2h.
We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLELocked door on Saleve side.
Proposal top remove the cylinder to avoid the guard locking the door during night times. -> Cylinder HAS BEEN REMOVED
-
-