o Assumption to maintain for all WPs the current baseline planning (keeping delay entirely as contingency) and assess eventual storage needs and cost consequences in 2024;
o Resources management by end of the HL-LHC Project (FSUs, MPA, Staff).
o Can some of the high-risk items be retired by re-arranging the production?
o Opportunities and consequences of re-profiling of the spending profile.
o Possible gains in MPA due to replacement by staff in 2024?