FASER Installation
Wednesday 10 Mar 2021, 09:00
→
11:00
Europe/Zurich
09:00
→
09:01
Videos
1m
Speaker
:
Jamie Boyd
(
CERN
)
20210315_092722.mp4
20210315_092808.mp4
Cabling (10/3)
Cabling/Cooling installation (11/3)
Cabling/Cooling work (15/3)
Cabling/Testing (12/3)
Cooling (16/3) (part 1)
Cooling (16/3) (part 2)
Photoshoot / Testing (18/3)
Tracker Installation (8/3)
Tracker testing (17/3) (part 1)
Tracker tests (17/3) (part 2)
Tracker transport over the LHC
Upper Frame Construction (9/3)
09:01
→
09:02
Edited Time Lapse Video
1m
FASER Installation.mp4
Video
09:02
→
09:04
Pictures (March 8/9/10)
2m
Speaker
:
Jamie Boyd
(
CERN
)
FASER-Installation-March2021.pdf
09:04
→
09:06
Current schedule
2m
Speaker
:
Jamie Boyd
(
CERN
)
FASER-Updated-Installation-Schedule_11.3.21.pdf
FASER-Updated-Installation-Schedule_15.3.21.pdf
09:06
→
09:08
Pictures (March 11/12/15/16/17)
2m
Speaker
:
Jamie Boyd
(
CERN
)
FASER-Installation-March2021-2.pdf
09:08
→
09:10
First Cosmic Ray events in TI12
2m
From the night of 18/19 March
vp1_faser_run1332_evt10841_2021-03-18T14-02-03_3.png
vp1_faser_run1332_evt10841_2021-03-18T14-02-03_4.png