- Working with ADC to move 3.8PB of MAS storage as DATADISK like in order to meet 2021 pledges while disk purchase is being processed. Timescale ~1-2 weeks.

- 2021 disk purchase released 8/16. Delivery mid-October.

- 2021 CPU purchase released 8/26. Delivery timescale 2-3 months.

- 2022 purchases will be released early FY22 in order to meet WLCG April 1st, 2002 milestone. 

- All new purchases will be deployed in new data center.

- HPSS core will be moved to new data center in October (after WLCG Tape test): 1 day HPSS downtime.