Commissioning of the GIF beam dump:
Proposed date: Beginning of July (just before NA physics)

We should be ready to give feedback, e.g. counting rates etc.

Week 27 - NA Setup : Beam line zones need to be CLOSED.
Nikos will contact us when we can enter the bunker.

Version 1.0 of schedule for GIF & RD51 (5 weeks):

12-20 July (first 9 days)
8-14. September (1 week)
20.10 - 2.11 (2 weeks)
10-14.11 (4 days)

Planning for the first beam slot completed.

CALL for RUN COORDINATORS  from the systems included in the beam time !

Requirements for the control room still needs to be defined.