WILL BE UPDATED DURING THE MEETING !!!
----------------------------------
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
Next beam pipe installation : 29.09.2021
----------------------------------
ATLAS - MM :
Maxence will be here the whole August.
SM1-M40 placed uprigth in front of Irradiator (Downstream)
After Testbeam, a new ATL-MM-CSC chamber would be installed inside the bunker for one month. It should be installed on the back of the ATL-MM ceiling chamber. Premixed bottles (Ar-CO2 80/20) already ordered.
15.09 - Changing the hanging setup.
CMS - CSC: Replacement of wheels done. Thanks to EP-DT for mass flow controller calib.
The setup moved back into bunker.
Gas chromatograph analysis to be performed during next week.
ATLAS - sTGC :
Currently not present in bunker.
ATLAS - sMDT :
Back to the nominal position since Sunday 15th. Minor adjustments still needed before the test beam. Gas rack ok, after the power cut (AULs test). Source OFF needed today for 1h.
EP-DT2 :
Setup moved back inside bunker. Same place as last test beam.
Filter scan planned for this afternoon. Filter scan on both sides.
EcoGas: running with standard gas mixture. Two chambers where removed and transported to 904 for further tests. Back on the GIF++ bunker before September test beam.
CMS-DT: Source scan scheduled for today. Will move into beam next Wednesday.
CMS-RPC: Consolidation system is ON for the longevity program. 2 chambers installed for test beam.
ATLAS-RPC: Module A0 has been inserted in the bunker. Being connected for test beam. -> IMPACT needed.
ProTOV: Will stay in H8 dump area.
RHUM: Arrived & installed downstream.