Commissioning of the GIF beam dump:
Originally proposed during the last days of beam setup, it needed to be shifted due to the problems with starting the NA Physics. We still need to find a time during the year for this.

Current schedule for GIF & RD51:

12-20 July (first 9 days)  - FINISHED
8-14. September (1 week) - In preparation
20.10 - 2.11 (2 weeks)
10-14.11 (4 days)

Latest schedule (2.2) attached. No major changes affecting GIF.
15-17.09 - Technical Stop 1 (TS1)
Beam pipe re-installation : 29.09

Plan for next beam time :