Very Important Dates :
NA physique 2022 will start around Mon 11.04.22 (probably postponed)
Annual Irradiator Maintenance : 10-14.01.2022
(DSO Test Thu. 13.01)
EHN1 De-cabling : 19.01 - 23.02. 2022
Details to be sorted out, but operation of the GIF looks feasible.
Flammable gases most likely not available (except premixed).
-----------------------------------------------------------------------------
Important Dates :
16-18.11 & 23-24.11 : Installation of supervision system. Irradiator OFF during day times.
Installation of cooling lines in preparation area.
30/11/21 - Test Normal/Secured (6h to 6h10) - CERN wide power cut (!!!)
DSO tests EHN1 + EHN2 + TCC8 + ECN3 BE-ASR 2 days Fri 04.03.22 13:00 Tue 08.03.22 12:00
CV Interventions :
Cooling tower degrade mode EN-CV 15 days Mon 15.11.21 08:00 Fri 03.12.21 17:00
Cooling tower off for maintenance EN-CV 20 days Mon 06.12.21 08:00 Fri 14.01.22 17:00
Cooling tower degrade mode EN-CV 10 days Mon 17.01.22 08:00 Fri 28.01.22 17:00
-----------------------------------------------------------------------------
AUG Test EHN1 :
Tests AUG BA80 (no access) EN-EL 1 day Tue 18.01.22 08:00 Tue 18.01.22 17:00
Tests AUG BA81 (no access) EN-EL 1 day Wed 19.01.22 08:00 Wed 19.01.22 17:00
Tests AUG BA82 (no access) EN-EL 1 day Thu 20.01.22 08:00 Thu 20.01.22 17:00
Meyrin West Area (e.g. 180): Sa. 11.12.2021
Meyrin Admin. Area : 4.01.2022
-----------------------------------------------------------------------------
AUL Test and electrical safety inspection:
Few minor issues were found. To be closed when recommendations are implemented.
----------------------------------------------------------------------------
GIF pyTIMBER :
Temporary solution http://epdtdi-pytimber-gifpp.cern.ch:8080/app only accessible through the CERN GPN.
Original site ( https://epdtdi-pytimber.web.cern.ch/app/gifpp ) stays deployed for the DIP/DIM live values, also accessible from outside through SSO.
----------------------------------
GIF Logbook & elog :
Discussion ongoing. Not yet all needed features are implemented.
Not for this beam time.