Very Important Dates :

NA physique 2022 will start around  Mon 11.04.22  (probably postponed)

Annual Irradiator Maintenance : 10-14.01.2022
(DSO Test Thu. 13.01)

EHN1 De-cabling : 19.01 - 23.02. 2022
Details to be sorted out, but operation of the GIF looks feasible.
Flammable gases
most likely not available (except premixed).

-----------------------------------------------------------------------------  

Important Dates :

16-18.11 & 23-24.11 :  Installation of supervision system. Irradiator OFF during day times.
Installation of cooling lines in preparation area.

30/11/21 - Test Normal/Secured (6h to 6h10) - CERN wide power cut (!!!)

DSO tests EHN1 + EHN2 + TCC8 + ECN3  BE-ASR    2 days    Fri 04.03.22 13:00    Tue 08.03.22 12:00

CV Interventions : 
Cooling tower degrade mode             EN-CV    15 days    Mon 15.11.21 08:00    Fri 03.12.21 17:00
Cooling tower off for maintenance    EN-CV    20 days    Mon 06.12.21 08:00    Fri 14.01.22 17:00
Cooling tower degrade mode             EN-CV    10 days    Mon 17.01.22 08:00    Fri 28.01.22 17:00
-----------------------------------------------------------------------------  

AUG  Test EHN1 :

Tests AUG BA80 (no access)    EN-EL    1 day    Tue 18.01.22 08:00    Tue 18.01.22 17:00
Tests AUG BA81 (no access)   EN-EL   1 day    Wed 19.01.22 08:00    Wed 19.01.22 17:00
Tests AUG BA82 (no access)    EN-EL    1 day    Thu 20.01.22 08:00    Thu 20.01.22 17:00

Meyrin West Area (e.g. 180): Sa. 11.12.2021

Meyrin Admin. Area : 4.01.2022

-----------------------------------------------------------------------------  

AUL Test and electrical safety inspection:

Few minor issues were found. To be closed when recommendations are implemented.
----------------------------------------------------------------------------

GIF pyTIMBER  :  
Temporary solution  http://epdtdi-pytimber-gifpp.cern.ch:8080/app  only accessible through the CERN GPN.
Original site ( https://epdtdi-pytimber.web.cern.ch/app/gifpp ) stays deployed for the DIP/DIM live values, also accessible from outside through SSO.

----------------------------------

GIF Logbook & elog  :   

Discussion ongoing. Not yet all needed features are implemented.
Not for this beam time.