Benchmarking Collection Campaign

  1. The end of the campaign is nearing
  2. Check machine configurations for missing entries

HEP-Workloads readiness

  1. IGWN:
    1. Validated. Ready to be executed for the 'matrix'
    2. Clarification needed about the limit of 80% of load reached (Josh is checking with the IGWN sw developers)
  2. Alice gen-sim-reco
    1. Reco step continues to fail. Alice experts are investigating.
    2. Meanwhile the Alice gen-sim-digi WL container image has been released
      1. Validation of Alice gen-sim-digi already started
  3. Atlas real-reco
    1. New WL proposed by Atlas.
    2. Build procedure in place, but still fails for an issue in the Atlas DB file (being fixed by Walter)