Next meetings : 

Important Dates :

Christmas Closure : 22-12.2021 to 4.01.2022
Stop of gas system (except Ar/CO2 flushing) on FRIDAY 17.12   Restart on 6/7.01
Strictly no access to the bunker from 21.12 16h until morning of 6.12.

IMPACT activities : Renewal for 2022 !
As each year, we will close the active IMPACT declaration over Christmas.
Please clone your activities, update them (!) and resubmit.

Annual Irradiator Maintenance : 10-14.01.2022
(DSO Test Thu. 13.01)

EHN1 De-cabling : 19.01 - 23.02. 2022
Lockout starting on the 14.01 (!)

Details to be sorted out, but operation of the GIF looks feasible.
Flammable gases still need confirmation if
available (except premixed).

Cooling tower off for maintenance    EN-CV    20 days    Mon 06.12.21 08:00    Fri 14.01.22 17:00
 

NA physique 2022 will now start - Week 17 (25.04)

-----------------------------------------------------------------------------  

AUG  Test EHN1 :

Tests AUG BA81 (no access)   EN-EL   1 day    Wed 19.01.22 08:00    Wed 19.01.22 17:00

Meyrin West Area (e.g. 180): Sa. 11.12.2021
Meyrin Admin. Area : 4.01.2022

DSO tests EHN1 + EHN2 + TCC8 + ECN3  BE-ASR    2 days    Fri 04.03.22 13:00    Tue 08.03.22 12:00