- Scintillator Irradiation for CMS HGCAL Detector.

BLM measuring campaign announced / ≈ 100 BLM, 6h approx. Week 45 (November 2nd till Friday 6th ). We will arrange everything in a way that the setup could be installed inside the bunker in the upstream area near ATL-sTGC setup    -> postponed until next year

----------------------------------

Bulgaria academy of science -> testing of new type of radiation monitor system

A new setup of ALICE-RPC will come. More news in coming weeks.

Lab on Fiber (LOF) dosimeter

Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)