Important Dates :
Annual Irradiator Maintenance : 10-13.01.2022 (DSO Test Thu. 13.01)
AUG Test EHN1 : BA81 (no access) EN-EL 1 day Wed 19.01.22 08:00 Wed 19.01.22 17:00
DSO tests EHN1 + EHN2 + TCC8 + ECN3 BE-ASR 2 days Fri 04.03.22 13:00 Tue 08.03.22 12:00
EHN1 De-cabling : 19.01 - 23.02. 2022 - Lockout starting on the 14.01 (!)
After a lot of negotiations, the GIF++ will stay operational most of the time.
Cooling tower off for maintenance EN-CV 20 days Mon 06.12.21 08:00 Fri 14.01.22 17:00
NA physique 2022 will now start - Week 17 (25.04)
IMPACT activities : Renewal for 2022 !
No access to the bunker area without IMPACT & activated operational dosimeter.