TREX 06-04-2022 Preliminary minutes (zoom meeting recorded by FSG)

Totem PPS

Q-FSG - How long would take the May installation

A-JB - 2.5days based on the experience (installation and connection of all the services)

Q-JS Alignment of the XRPs is only related to the detector package or full pot units?

A-JB To be seen based on the beam position, but it is possible. Standard approach will apply (x-rays of the VMs)

Q-MBM Next YETS planning?

A-JB - No special request on the top of the standard maintenance.

AFP ALPHA

C-JS the same x-rays strategy as for Totem PPS applies.

C-MR - Slides missing on then INDICO

ZDC

Q-MBM - TS activities are for special TS LHCb or TS2

A-SP - Activities foreseen TS2 - September 2022

SND

Q-FSG - Emulsion bricks are still empty.

A-PSD - Will be installed tomorrow.

ZDC-RPD

C-FSG - Detailed discussion is needed (Francisco will organize this one).

C-MR - Documentation should be uploaded to ATLAS repository.

A-RL - It will be corrected.

Q-SP - ZDC team should be on the loop of these activities to avoid any schedule issues.

A-FSG - TREX will include the ZDC team on the loop.

BRAN

- No comment / feedback provided at the moment.

FASER

Q - FSG - Is the special access coordinated with Jorg?

A-BP - Yes it is.

---

Minutes written by J. Sestak 06-04-2022