FP420 Meeting - CERN
from
Thursday 8 February 2007 (09:00)
to
Friday 9 February 2007 (18:00)
Monday 5 February 2007
Tuesday 6 February 2007
Wednesday 7 February 2007
Thursday 8 February 2007
09:30
Introduction and communications
-
Albert - Brian
Introduction and communications
Albert - Brian
09:30 - 09:40
Room: 40/R-A10
09:40
Hamburg pipe
-
Krzysztof
Hamburg pipe
Krzysztof
09:40 - 10:00
09:40 - 12:50
10:00
Detector mechanics
-
Ray
Detector mechanics
Ray
10:00 - 10:20
10:20
Latest on Cryostat design
-
Keith
Latest on Cryostat design
Keith
10:20 - 10:40
10:40
Discussion on Cryostat Design
-
ALL
Discussion on Cryostat Design
ALL
10:40 - 11:00
11:00
Station's layout - alignment
-
Jo
Station's layout - alignment
Jo
11:00 - 11:20
11:20
Detector and Near electronics
-
Scott
Detector and Near electronics
Scott
11:20 - 11:40
11:40
Status: HV and LV supplies
-
Henning
Status: HV and LV supplies
Henning
11:40 - 12:00
12:00
Thermal Model
-
Berend
Thermal Model
Berend
12:00 - 12:20
12:20
Cooling System
-
Jaak
Cooling System
Jaak
12:20 - 12:40
12:40
break
break
12:40 - 14:10
14:10
14:10 - 17:40
Room: 40-S2-B01
Infrastructure
-
Detlef
Infrastructure
Detlef
14:10 - 14:30
14:30
Radiation Monitoring in the proximity of 220 and 420m
-
Thjis Wijnands
Radiation Monitoring in the proximity of 220 and 420m
Thjis Wijnands
14:30 - 14:50
14:50
the remotely moveable ALICE ZDC using the LHC collimator motor control system
-
Thorsten Gallmeister
the remotely moveable ALICE ZDC using the LHC collimator motor control system
Thorsten Gallmeister
14:50 - 15:10
15:10
ATLAS and CMS 220m integration - Discussion
-
ALL
ATLAS and CMS 220m integration - Discussion
ALL
15:10 - 17:40
18:00
CB
CB
18:00 - 18:30
Friday 9 February 2007
09:00
09:00 - 18:00
Room: 40/R-B10
10:00
Gamma to Zp
-
Jeff
Gamma to Zp
Jeff
10:00 - 10:10
10:10
FP420 data processing and integration into CMS
-
Vladimir Popov
FP420 data processing and integration into CMS
Vladimir Popov
10:10 - 10:25
10:25
Development of G4-FP420-3DSI simulation
-
Sasha
Development of G4-FP420-3DSI simulation
Sasha
10:25 - 10:40
10:40
Background Devlopments
-
Andrew
Background Devlopments
Andrew
10:40 - 11:00
11:00
Timing Update
-
Andrew
Timing Update
Andrew
11:00 - 11:20
13:00
break
break
13:00 - 14:30
14:30
Discussion on Infrastructure requirements - AOB
-
ALL
Discussion on Infrastructure requirements - AOB
ALL
14:30 - 17:00