DOFRS for NA/ECN3 - 15 June 2022

Present: Y. Kadi/NA-CONS; M.Fraser, J. Bernhard; R. Garcia/R2E; D. Di Francesca, D. Ricci/EN-EL  

Point in bold below were the agenda of the meeting:

1- Understanding of the requirements for dose-monitoring in the areas from TCC2/TDC2 up to ECN3

NA-CONS confirms that DOFRS will be needed at term for dose monitoring (precise areas to be defined). D. Ricci: the baseline so far is to install the cable tray/tubes infrastructure during Phase 1 (LS3) in TDC2/TCC2, with an option to install also fibres and interrogators (to be confirmed upon preliminary studies on radiation levels).   

Concerning ECN3 ongoing studies, there is a need to assess the beam dynamics in P42 (i.e. the beam line spanning from TT83 to TCC8). That should be done in 2022-24 to serve as an input on how to optimise the beam line for the future physics experiments in ECN3.  Possible solutions were considered during the discussion, including:

  1. Design and deployment of a DOFRS system (~700m ) during YETS 2022, including its operation (maintenance & data extraction) during the following years;
  2. Deployment of BLMs during YETS 2022 along the beam line 
  3. Placement of RPL passive dosimeters in strategical positions (during YETS 2022)
  4. Deployment of RADMON/BATMON (possibly working via wireless or on battery)
  5. Deployment of passive fibre sensors (reading them out with an OTDR during technical stops)
  6. Deployment of -novel type- TIMEPIX BLMs (only a couple to cross-reference the other deployed sensors)

2- matching of the requirements with existing tools/methods/strategy/resources 

Solution (B) would be ideal but was a priori excluded, imagining the constraints for deploying and cabling all the BLMs

Solution (A) was hence identified as a more feasible option. Nonetheless, the following points are to be considered when analysing the details of its feasibility:

Solutions (C) (D) E) (F) can be instead exploited either singularly or in combination, entailing a reduced effort w.r.t. to (A) and (B), while offering valuable data for both ECN3 studies and DOFRS studies (aiming at future system deployment).

Preliminary conclusions and actions:

3- matching of the requirements with NA-CONS project strategy/resources, in particular w.r.t. Phase 1 and Phase 2 already targeted activities

Action Daniel/Diego+Yacine: to look into DOFRS needs at term for all NA-CONS areas. Confirm the objective for Phase 1 and pre-estimate activities for Phase 2. Propose priorities by areas, to cope with limited resources.

4- A.o.B

None.

Minutes taken by D. Ricci