PRR (Production Readiness Review) for MQ coils production at TESLA
Friday 8 July 2022 -
09:00
Monday 4 July 2022
Tuesday 5 July 2022
Wednesday 6 July 2022
Thursday 7 July 2022
Friday 8 July 2022
09:00
Description of MQ magnet coils
Description of MQ magnet coils
09:00 - 09:15
09:15
Interfaces (managerial and technical)
Interfaces (managerial and technical)
09:15 - 09:30
09:30
Quality Plan (general and specific)
Quality Plan (general and specific)
09:30 - 09:45
09:45
Manufacturing and Inspection Plan
Manufacturing and Inspection Plan
09:45 - 10:00
10:00
Break
Break
10:00 - 10:10
10:10
Fabrication Procedures, Manufacturing Drawings
Fabrication Procedures, Manufacturing Drawings
10:10 - 10:25
10:25
Material and components procurement plan
Material and components procurement plan
10:25 - 10:40
10:40
Infrastructure and tooling availability at the Contractor premises
Infrastructure and tooling availability at the Contractor premises
10:40 - 11:00
11:00
Polymerisation mould recovery plan
Polymerisation mould recovery plan
11:00 - 11:25
11:25
Production schedule and associated resources
Production schedule and associated resources
11:25 - 11:45