TCC:
- Julabo equipment will arrive max 3rd week of January
- Protection cover under production
- A test to remove water avec TCC test must be done
BPM flanges:
- Tomography will be performed on the connectors once the connector will be extracted. A connector that is leaking after welding will be analysed. Not started.
RF fingers:
- Support ongoing, fingers under chemical cut
- Adjust length of the RF fingers testbench
Design:
- DN300 flanges with pinch-off: waiting the CDD from VSC
- Jaw flatness measurement tool -> give the CDD to Dylan for the tooling list
- TCLP, TCSPM, TCTPM folders: not started
- Post-proto modifications regarding Dylan’s Excel: ongoing for jaws, done for mechanical table, almost finished for feet
- Switch integration: drawing to be done
- TCTPXV review and modifications for serie: Emanuel working on it
- Mechanical table procedure check: ongoing
- Gabarit for cooling pipes production: ongoing, wait for comments
- Copper wedges for jaws posing during vacuum test (STI)
- Check if we can use the same jaw design for TCTPXH as TCLPX (1 week)
- Mock-up integration: discussing about the responsibilities beginning of next week
Assembly:
- TCLPX jaws under metrology to perform flatness measurements post-bakeout
- TCTPXH jaws disassembled, and copper parts came back from metrology -> everything good
- Tank sub-components assembled, waiting for the tanks
- Mechanical tables ready for assembly
- Vireur is ready in clean room
- Propose a date for Gregory and Jan for assembly test of the interconnects
Procurement:
- Inermet blocks production ongoing, arriving at CERN mid-February
- CuCr1Zr taperings ordered to DEM
Production MME:
- First tank leak test done and ok. Second one ongoing. Hydraulic actuator must be added to avoid DN300 flanges to pull on the bellows. First delivery om Monday then on Tuesday
- Tanks metrology to be sent by Emilien
- Tank cover arriving later
- Nanoker will re-machine the wrong blocks
Production STI:
- Jaw flatness measurement tool: ongoing, try to get them for TCLPX measurements
- Remaining feets components: ongoing
- Transitions and pinch-off: not started
- Lifting ears: not started
- Taperings for end of January
Update on planning:
- Add a dummy assembly of the second TCTPXH jaw with copper diamond parts
Update for the serie:
- Create a tool to avoid DN300 to pull bellows during tank leak test
- Reduce height and width of the clamps