ACTION TO BE DONE:
- STI will re-assemble TCTPXH for good positioning of the sttifeners.
- Dylan will send TCLPX jaws screen to Carlotta and Luisa.
- Emilien shall put a report on the indico regarding tomography.
- Luca shall update reference available on website for the TCTPXH washers.
- Dylan will send data to Luisa for simulations.
- Gabarit should be send to Emilien as soon as possible.
- Romain will cut M4x35 A4-100.
- Emilien will bring the tank covers next time (TCLPX bending slot).
OTHER ACTIONS:
TCC:
- Several test ongoing to validate the testbench and for Luisa and Carlotta (with all the data).
- Some data shall be clarified between Dylan and JMQ.
- JMQ will test automatic cycles.
BPM flanges:
- Tomography done, the welding of the connector itself is good, we cannot see the inside (ceramic) -> Difficult to give a conclusion here (check attached report).
- 4 new flanges under production to re-launch test -> A discussion with AP and STI and BI will be organized. 1 flange ongoing in machining to test welding with passive cooling with TIG. SubD9 ordered by Jerome.
RF fingers:
- Romain launch silver plating: 2x5mm, 1x10mm, 1x15mm. EBW ongoing.
- Adjust length of the RF fingers testbench.
Design
- TCLP, TCSPM, TCTPM folders: not started.
- Post-proto modifications regarding Dylan’s Excel: ongoing for jaws, done for mechanical table, almost finished for feet
- TCTPXV review and modifications for serie: Emanuel working on it
- Mechanical table procedure check: ongoing
- Gabarit for cooling pipes production and assembly: ongoing
- TCLM masks
- Copper wedges for jaws posing during vacuum test (STI)
Assembly:
- TCTPXH jaws re-assembled without blocks to do a fake insertion in the tank.
- TCLPX waiting for re-bending.
Procurement:
- Inermet blocks production ongoing, arriving at CERN End of March.
- Nanoker will re-machine the wrong blocks
Production MME:
- Tank cover arriving mid-March (input from Emilien) then cleaning.
- Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118
- BPM leaking flanges to solve with passive cooling.
- RF fingers
Update on planning:
- Collimators shall be operational for July.
- TCLPX prevision: Mid-October
- TCTPXH prevision: Beginning of November
- RF fingers, Inermet, BPM flanges, TCC test bench are on the critical path.
- Cooling for April
Update for the serie:
- Check to put an elastic element as TCLPX for TCTPXH and avoid overlength of the blocks.
- Define a probe cable length for serie with Jerome.
- Put sliding contact for BPM clamps.