Both ALFA and AFP fully commissioned/qualified by a full set of movement system tests and ready to be inserted for first beams in 2023.

  1. Test of injection permit (lost when pot moved outside of HOME position) - no failure observed.
  2. Test of the response to the LVDT-to-limits comparison (inner dump and warning limits) - no unexpected behavior observed.
  3. Test of User_Permit and automatic pot extraction as a function of all input flags - test omitted (done in 2022) since there were no changes in the LHC interlock system concerning input flags (decided by MPP to be dropped).
  4. Test of the LVDT bypass box - no failure observed.
  5. Test of Hardware and Software buttons (extraction by DCS & emergency extraction by HW button) - AFP reacted as expected, ALFA failed due to an older PXI crate type, as expected; no failure observed.

MPP checklist signed-off in the commissioning tool. All tests summarized in the attached draft EDMS; final version to be sent around (also updated in the agenda).