Both ALFA and AFP fully commissioned/qualified by a full set of movement system tests and ready to be inserted for first beams in 2023.
- Test of injection permit (lost when pot moved outside of HOME position) - no failure observed.
- Test of the response to the LVDT-to-limits comparison (inner dump and warning limits) - no unexpected behavior observed.
- Test of User_Permit and automatic pot extraction as a function of all input flags - test omitted (done in 2022) since there were no changes in the LHC interlock system concerning input flags (decided by MPP to be dropped).
- Test of the LVDT bypass box - no failure observed.
- Test of Hardware and Software buttons (extraction by DCS & emergency extraction by HW button) - AFP reacted as expected, ALFA failed due to an older PXI crate type, as expected; no failure observed.
MPP checklist signed-off in the commissioning tool. All tests summarized in the attached draft EDMS; final version to be sent around (also updated in the agenda).