Fresca 1:
- new test from next week
- potential end of test: end of June
Fresca 2
- WWC from EN-EL: they will be installed in mid July
- Cables cryo-instrumentation (2 weeks): beginning of July to be confirmed (Florian Girardot will contact CRG)
- Protection of compensator: design approved by SC. Procurement to be launched.
Scan of the zone to be foreseen at the end of July