Wrap-up of hardware commissioning 2011
Tuesday 8 March 2011 -
09:00
Monday 7 March 2011
Tuesday 8 March 2011
09:00
Introduction
-
Nuria Catalan Lasheras
(
CERN
)
Introduction
Nuria Catalan Lasheras
(
CERN
)
09:00 - 09:20
Room: 30/7-010
09:20
600 A circuits resistance measurements.
-
Edward Nowak
(
CERN
)
600 A circuits resistance measurements.
Edward Nowak
(
CERN
)
09:20 - 09:40
Room: 30/7-010
09:40
RQT13.L7B1 NC and electrical measurements.
-
Mateusz Bednarek
(
CERN
)
RQT13.L7B1 NC and electrical measurements.
Mateusz Bednarek
(
CERN
)
09:40 - 10:00
Room: 30/7-010
10:00
RCO.A45B1 NC and quench-like event.
-
Arjan Verweij
(
CERN
)
RCO.A45B1 NC and quench-like event.
Arjan Verweij
(
CERN
)
10:00 - 10:20
Room: 30/7-010
10:20
Current leads regulation during PGC
-
Sandrine Le Naour
(
CERN
)
Current leads regulation during PGC
Sandrine Le Naour
(
CERN
)
10:20 - 10:40
Room: 30/7-010
10:40
PNO analysis tool and NCs.
-
Giorgio D'Angelo
(
CERN
)
PNO analysis tool and NCs.
Giorgio D'Angelo
(
CERN
)
10:40 - 11:00
Room: 30/7-010
11:00
Orbit correctors trips during PGC
-
Michele Modena
(
CERN
)
Orbit correctors trips during PGC
Michele Modena
(
CERN
)
11:00 - 11:20
Room: 30/7-010
11:20
RSS.A78B1 quench-like events during PGC
-
Markus Zerlauth
(
CERN
)
RSS.A78B1 quench-like events during PGC
Markus Zerlauth
(
CERN
)
11:20 - 11:40
Room: 30/7-010
11:40
RQ6.L3B2 and RQ6.R7B2 quenches after commissioning.
-
Andrea Musso
(
CERN
)
RQ6.L3B2 and RQ6.R7B2 quenches after commissioning.
Andrea Musso
(
CERN
)
11:40 - 12:00
Room: 30/7-010
12:00
RQTL9.L7B1 quenches after commissioning
-
Jean-Philippe Tock
(
CERN
)
RQTL9.L7B1 quenches after commissioning
Jean-Philippe Tock
(
CERN
)
12:00 - 12:20
Room: 30/7-010