Minutes of the PS-SPS Users Meeting for Week 26 held on June 29th, 2023

Physics Coordination from 24th June to 4th July by Martin Jaekel. Send email to spsco@cern.ch

Next user meeting:
For week 27 on Thursday, July 6th, 2023 10:30 CEST
Meeting room 874/1-011

News from the PS & SPS Physics Coordinator (M. Jäkel)

See this codimd location from Tuesday morning onwards for the News from the FOM

AD/ELENA

Preview of Booster inspections - no beam from 7:30 to 9:00.

This stops might be cancelled, if the inspections could be performed during other down-times.

• w26, on Thursday 29th June.
• w28, on Thursday 13th July.
• w30, on Thursday 27th July.
• w33, on Monday 14th August.
• w35, on Thursday 31st August.
• w37, on Wednesday 13th September.
• w39, on Thursday 28th September.
• w41, on Wednesday 11th October.

Preview of next weeks MDs:

Week 26:

Week 27:

Week 28:

Insity split

Starting FRIDAY 30.6 : (to be updated)

PS Machine Report (B. Mikulec)

SPS Machine Report (Kevin)

Safety / Radiation Protection (J.Devine)


n_TOF (Nikolas Patronis)

East Area Beam Status (N. Charitonidis)

T09: Operation ongoing. XBPF readout issues last weekend due to a software update. Beam to be checked with IDEA DRC on Thursday.
T10: Operation ongoing. Some issues with magnet T10.BHZ027, being monitored.
T11: No operation just now.

East Area Users Tour de Table

T8: IRRAD / CHARM (F. Ravotti & S. Fiore)

Similar week as the previos one due to the reduced PS beam availability (see cumulative T8 intensity plot below). On Friday and Monday MD cycle was activating the EAST_T8 user timing making trigger the IRRAD instrumentation when no beam: issue promptly investigated and solved by PS-OP. During the access on Wednesday we exchanged dosimetry and all long-term users continue EP-ESE, TE-MSC, CMS Pixel, ATLAS ITk strips, etc. (IRRAD). ATLAS and CMS removed their setups, TE-MPE, BE-CEM users modified their setups and continue testing (CHARM). Beam alignment on both X- and Y-axis only ~83% over the week (e.g. lower than the 96%-97% during the first weeks, but testins UCAP steering [see PS report]). Upcoming access, next week.

T9 Outgoing: MUONE ECAL (Carlo Ferrari)

We had one whole week (one day more than scheduled).
Despite of the problems at the accelerator on Wed/Thu of last week and on Tue of this week, we could accomplished almost completely the physics program we planned.
We could scan the entire ECAL module at some energies between 1 and 6 GeV.
We tried to take data at 10 GeV, where the electron content in the beam is very low. Effectively, we could tag the electrons with the Cherenkov beam detector, at a rate of few tens/spill. We acquired some thousands events, enough, we hope, to have a reference point.
On Wed morning we de-installed the apparatus, and cleaned the area and the control room. Then we moved the apparatus to the M2 beam line, and re-installed there, for a parasitic (technical) test with AMBER.

T9: IDEA DRC (Shuichi Kunori)

We brought several types of fibers and SiPMs, and readout electronics from Texas Tech University. The goal of our test was described in our preliminary report last week (in pdf). We will complete the installation of the hardware by 15:30 before the safty clearance inspection. Once the inspection is done, we start taking data with eleveton beams and then use hadron beams.

T10: IDEA CC (Franco Grancagnolo, Nicola De Filippis)

We experienced some toubles with the DAQ system for our detector last week but then we found the solution and the configuration has been working and stable since sunday night. We observed lower rate of muons than expected in the past days, likely related to a magnet turning faulty along the beam line. Due to the power cut yesterday we lost 3/4 of one data taking day. After that we got the beam and we have been taking data smoothly so far. Anyway we would report about a general instability of the beam that makes hard to make plans for the tests/measurements.

T10 Incoming: ALICE ITS3 - Week 27 (Please Add Your Name Here)

T10 Incoming: ALICE TIMING - Week 27 (Please Add Your Name Here)

North Area Beam Status

H2, H4, H6, and H8 Beams (N. Charitonidis)

H2/H4: Normal Operation, no particular issues.
H6: No issues.
H8: Beam set up Wednesday evening for first electron users this year, tentatively looks OK.

Other Beams P42, K12, and M2 (N. Charitonidis)

M2: Operation ongoing without problem. On Friday AMBER DY test is planned. RP test scheduled to start tentatively around 14:00.
K12/P42: SHADOWS test completed on Monday.

North Area Users Tour de Table

P42-K12 and M2

K12: NA62 (L. Bician)

M2: AMBER (Maxim Alexeev)

The core part of the first running period dedicated to the antiproton cross section measurement has been concluded on Sunday 25.06.23.
We have emptied the target and are presently taking some reference empty target measurements that should be concluded on Friday 30.06.23. The same day a test to validate with our Radioprotection colleagues the high intensity 3108

part/s beam in 888 will take place. The spring-summer AMBER running period will be concluded by a ~4 days high intensity test stopping on Tuesday 8:00 04.07.23.
Observations:

  1. Last days issues with the beam are making harder to conclude the empty target data sample within 14:00 of Friday 30.06.23.
  2. CEDARs operation and fine tuning will be critical for the high intensity running. For the moment it is almost impossible to set in a stable way a small opening of the diaphragm and to position the CEDAR in a reliable way. We know an intervention is planned to address the issue, will be very important for us.

Request:

  1. To be on the safe side a 3 spills SC till Friday would be helpful.
  2. Conditionally to the test with the RP colleagues we might need 100-120 units on the T6 to reach the requested intensities.

M2 Incoming Access Only: NA64mu - Week 27 (Please Add Your Name Here)

H2

H2 Main: LHCb ECAL (Loris Martinazzoli)

One quadrupole on the beamline failed overnight but was promptly reset by the beam physicists.Thanks to Bastien, Dipanwita, and Nikos for their support even over the weekend.

H2 Incoming: NA61/SHINE - Week 27 (Piotr Podlaski)

H4

H4 Main: NA64e (L. Molina)

We continued data taking last week. We had a couple of days without beam but we collected about 5x10^11 EOT. Today we moved to 70 GeV to positrons and tomorrow we plan to move to hadrons until the end of our run next Wednesday.

H4 Incoming Main: GIF++ - Week 27 (Martin J.)

Preparation for the beam time is going fine. We expect to participate with 11 setups in parallel. Proposal from RD51 about usage of Goliath and electron beam runs received. Hope to still be able to fine-tune this proposal with them.
Most setups already installed and running, some setups to complete installation during next week, ahead of the beam time.

H4 Incoming Parallel: RD51 - Week 27 (Yorgos Tsipolitis, Eraldo Oliveri)

H6

H6 Outgoing Main: AIDAInnova (Iván Vila Álvarez)

H6 Incoming Main: CMS MTD (Iván Vila on behalf of Roberta Arcidiacono)

H6 Parallel: ATLAS ITK PIXEL (Andre Rummler)

We finished the irradiated SCC batch at different inclinations taking most of the foreseen data points despite some issues (chiller stops; ill understoof flickering communciation issues with the modules).
On Wednesday we installed a new batch including an irradiated RD53B quad module. In order to achieve better cooling than last time we installed a complete secondary cooling circuit dedicated to the quad: drilled two holes in the box using RP vacuum cleaner; installed two hoses with armorflex going to Julabo FP-89 HL; two t-pieces inside the box; cooling two solid/liquid HX on the quad holder which are back cooling one peltier each. First test very successful after fixing two leaks which took a few hours longer: <-20°C on sensor powered instead of >+6°C. Today cooling tests with different settings to understand the system better and trying to start real measurements with the quad module.

Two irradiated SCCs (measured last time unirradiated in the test beam) arrived Tuesday at CERN; processing by RP the same late afternoon; thank you very much; delivery to EHN1 foreseen for Friday. Depending on how the works on the quad batch goes and on the program of the main user in H6B we would try to mount them as a third batch.

H6 Incoming Main: EP PIXEL (Justus Braach)

H8

H8 Outgoing Main: LHCb (Loris Martinazzoli)

Successful data taking for all the teams (Muons-RICH-TimePix4).

All set-ups uninstalled and areas freed.

H8 Outgoing Parallel: UA9 (Francesca Galluccio)

We could not complete our program.
We had few crystals more to test in several configurations.
Nevertheless, we could take some very useful data that will allow advancing in our RD.

H8 Main: IDEA DRC (Please Add Your Name Here)

Also: parasitic user behind H8 DUMP in week 26

H8 Incoming Main: ATLAS TILECAL (Giulio Usai and Tigran Mkrtchyan)

See slides attached in indico. In the 2023 campaign (2w starting now +2w in September) will continue the testing of electronics prototypes for HL-LHC and calibration studies.
The scanning table is in garage position and accessible from the back, We will be installing some new electronics in the modules and in the barracks in the next days and beginning of the next week.
on Wed 5th we will be dismounting the fences that close the garage and moving the table in the area.
Requested setup and configuration of the beam line is like last year.

Parasitic Users

Reporting for parasitic users is optional, please add your name below:

K12 Outgoing: SHADOWS (Please Add Your Name Here)

M2: MUonE tracker+ECAL (Carlo Ferrari)

We completed the installation with ECAL and chiller, we are ready to take data for the next week (without the chiller the temperature inside the tracker was too high to power the sensors).

H4 Incoming: STRAW TRACKER 3D (Please Add Your Name Here)

Also: current parasitic user behind H8 DUMP in Week 26

H4 Incoming: MINICACTUS (Please Add Your Name Here)

H6: EXFLU (Valentina Sola)

The setup is completed and safety visit done on 29/6 at 9:00.
Setup includes 4 to 6 DUTs read out by oscilloscopes, with power suppliers for HV/LV. Maximum HV will be -500 V.
Eventual usage of dry ice to cool down the devices, if needed.
High intensity beam required for end of this week / beginning of the next week.

H6: ATLAS MALTA (Please Add Your Name Here)

H6 Incoming: MONOLITH (Lorenzo Paolozzi)

High intensity beam required to run.
The setup will consist of the Geneva FEI4 telescope + two DUT boards + 2 MCP-PMT as time reference.
The DUTs are heavily irradiated silicon pixel sensors, they will be operated inside a cold box. tu

H8 DUMP: IDEA DRC (Roberto Ferrari)

Setting up of our detectors done. At 20 GeV the electron beam purity looks fine. Problems with both Delay Wire Chambers (no signal arriving) and with one Cherenkov counter. Waiting for the beam detector expert to come and look at the DWC signals. We definitely need the position information.

AOB

Minutes by the respective speakers, edited by E. B. Holzer and M. Schwinzerl