Minutes of the PS-SPS Users Meeting for Week 31 held on August 3rd, 2023

The agenda for this meeting is based upon user schedule v1.7.0, please cf. here. Please note the current injector schedule which contains information about MDs, Technical stops, etc. and can be found here.

Next user meeting:
For week 32 on Thursday, August 10rd, 2023 10:30 CEST
Meeting room 874/1-011

News from the PS & SPS Physics Coordinator (E. B. Holzer)

PS and SPS Physics Coordination:
August 4 to August 14: Martin Jaekel
August 15 to August 20: Dragoslav Lazic
August 20 to August 23: Martin Jaekel

EURO-LABS TA:
Email to all requestors will be sent out today or tomorrow:

  1. Financial conditions for PS & SPS Test Beam users (warning: differnt from standard conditions)
  2. Names of the visits which have already been approved by the USP
  3. Per individual email: details on the number of per diems approved per visit per person

Possibility to test one scheduled, dedicated AWAKE run (i.e. a period without SPS NA beam) in the comming week. Time to be defied for a period of not more than 4 hours (tbd).
- Please provide input, if you see a potential problem with that!

See this codimd location from Tuesday morning onwards for the *News from the FOM (E. B. Holzer

Preview of MDs:

Week 31

Intensity split and wobbling

Wobbling change August 9 to August 17:

T2 = 50
T4 = 48 / T10 = 28
T6 = 35

PS Machine Report (M. Fraser)

SPS Machine Report (F. Velotti)

Safety / Radiation Protection (Alex Schouten)


n_TOF (M. Bacak)

Physics according to planning:

Issues:

Proton beam excellent - making use of the different intensity variants now in several experiments (request will come today again).

East Area Beam Status (D. Banerjee)

T9: Beam preliminarily checked on Wednesday evening. Fine tuning to be done on Thursday following the safety clearance.
T10: User reported issues with magnet BHZ027, settled with some resets, otherwise good operation. Beam for ALICE TOF requested for Friday morning.

East Area Users Tour de Table

T8: IRRAD / CHARM (F. Ravotti, S. Fiore)

Very good week, no issue with operation. Cumulative intensity delivered to T8 again well above specifications, thanks! :) (~2.3e16 p/w, see plot below). Beam alignment and center on both X- and Y-axis, under control (more than 91% of the spills were centered within +/- 2mm on the horizontal [x] plane).

During the access on Wednesday, we exchanged dosimetry samples and replaced samples for most of the long-term users: EP-ESE, TE-MSC [including N2 experiment], CMS Pixel, ATLAS ITk Pixel [scanning table], RD50, ATLAS HGTD, etc. and installed a new experiment for SY-BI (setup with optic fibers). This installation and the setup of its DAQ required the T8 beam to be OFF until late in the afternoon (IRRAD). Removed setups by ATLAS and BE-CEM, installed new ones by BE-CEM and TE-MPE (CHARM).

Upcoming access, next week.

T9 Outgoing: WCTE (M. Hartz)

T9: TECHNO CLS (S. Carsi)

T10 Outgoing: BL4S (Sarah Zoechling)

Thank you very much for the additional week in T10 - we could really benefit from the extra beam time!

However, some issues to address or keep an eye on during our testbeam in September:

Huge thanks to Maarten van Dijk for his patient support and advice! And also to Inaki Ortega Ruiz to help us a lot on debugging the DWCs. And to everyone else who fixed whatever problems we experienced. BL4S would not be possible without many helping hands, including Dipanwita Banerjee, Johannes Bernhard and everybody else from the BE-EA group; the mechanical engineering department; Michael Lazzaroni, Aboubakr Ebn Rahmoun, David Jaillet et al from infrastructure services; Jocelyn Tan and everybody else at BI; and E. Barbara Holzer.

Outlook: Testbeam in September (Weeks 37 & 38) where two winning teams perform their experiements at CERN => If you would like to meet the students (e.g. just to say ‘hello’ or to support them during the data analysis), please let us know. The students and us, we would be super grateful and happy to meet you!

T10: ALICE ToF (Y. baek)


AWAKE (Giovanni Zevi Della Porta)

First week of proton run.
Commissioning of new Plasma Source is now complete, but took 3 days longer than expected, delaying the start of the proton run.
First beam expected today: diagnostics and alignment.
Tomorrow (Friday) we will load Rubidium in the system and begin the physics run.


North Area Beam Status

H2, H4, H6, and H8 Beams (D. Banerjee)

H2: NA61 continues with 120 GeV/c. Movement of the beam when other lines change files still present (less in 120 GeV/c). SY/EPC and TE/MSC following.
H4: Normal operation, CMS ECAL --> CMS HGCAL. No issues.
H6: Higher intensity week and PPE156 and PPE146 zones put together with access system change - now back to normal. After T4 target change on Monday we had to reduce the rate a bit in H6 to around 3.5e6 particles / spill in PPE156 to stay with in radiation alarms. Beam checks done and aligned on the CEDARs and alignment checked downstream.
H8: Extensive use of electron beams show strong correlation with T4 target length, good operation for POKER. First files prepared Wednesday evening for QFIB, and first test with beam performed with SND. Remaining files to be created and tested Thursday.

Other Beams P42, K12, and M2 (D. Banerjee)

M2: Stable operation continues. The MBPLs installed for NA64mu had wrong configuration of the power converters in CESAR which was fixed on 25th July, however the server held the old config so the change only took effect after the restart of the CESAR server on 2nd August during the MD. This was confirmed with the CESAR support.
P42/K12: Stable operation without issues. Smooth going back to kaon mode last Monday.

North Area Users Tour de Table

P42-K12 and M2

K12: NA62 (B. Velghe)

M2 Main: NA64mu (Vladimir Poliakov)

H2

H2: NA61/SHINE (Piotr Podlaski)

H4

H4 Outgoing Main: CMS ECAL (Chiara Amendola)

Spare CMS ECAL supermodule partially equipped (225 channels) with Phase2 electronics (front-end and back-end)

Scope:

We took a large amount of data with electron beam spanning in 20-300 GeV and tested the whole map of channels.

The ECAL supermodule will stay installed in H4 until the end of august (safety clearance already extended), and will stay operational for data-taking in pedestal and laser mode (while the rest of the equipment is disconnected).

Thanks for the support to everyone, in particular to Nikos and Bastien for H4 and to the safety team - we have been running smoothly and we consider the campaign very successful.

H4 Main: CMS HGCAL A. Steen

Installed HGCAL detectors (2 silicon detectors) yesterday in PPE134.
Installation went fine. Safety clearance visit done at 4PM.
Successfull operation of the detector from the control room but unfortunately only with internal trigger.
Plan for the next hours:

H4 Incoming Main: CMS ZDC EM S. Popescu

Preparation for test beam on-going:

H6

H6 Outgoing Main: EP PIXEL (Justus Braach)

H6 Outgoing Parallel: ALICE ITS3 (Paolo Martinengo)

quite successful data taking, excellent beam conditions
thanks a lot to our main/co-user for collaboration (we had a number of accesses)

H6 Main: ATLAS ITK PIXEL (Andre Rummler)

Setup finished yesterday with re-installation of secondary cooling circuit for one quad. Safety visit passed in the late afternoon. Unfortunately, there was an issue with the chiller which was stuck at -2°C. Recovered itself and was cold this morning but have to thermal cycle now as not enough cold delivered to HX (ice build up). More material arriving hopefully in the next couple days; will need another long access.

Meanwhile fixing (reinstalling) the ACONITE gateway computer which was reported during HGTD beam time.

H6 Incoming Main: ATLAS ITK STRIP (Jiri Kroll, John Keller)

Testbeam campaign is scheduled between August 9 and 16, the uploaded slides summarize out plans

H6 Incoming Parallel: MEDIPIX (Please Add Your Name Here)

H8

H8 Outgoing Main: POKER (L. Marsicano)

Very productive beam time!

H8 Main: QFib (Suat Ozkorucuklu suat@cern.ch)

Trigger and DAQ commissioning comleted
previous week. Already started taking data. Beam files we requested are almost
ready.

Started with 180 GeV pions 60k delivered, 48k obtained with coindences (3 beam defining conters of 10x10 mm each).
Once we complate 180Gev run plans, will change to 140GeV pios.

Later we will change to 50,75,100,125 GeV electron this weekend weekeed.

H8 Incoming Main: SND@LHC (marco.dallavalle@cern.ch)

see text further down


Parasitic Users

Reporting for parasitic users is optional, please add your name below:

M2 Outgoing: AMBER (Please Add Your Name Here)

M2 Outgoing: MUonE tracker+ECAL (Please Add Your Name Here)

H6 Outgoing: ATLAS MALTA (Please Add Your Name Here)

H6 Outgoing: MONOLITH (Please Add Your Name Here)

H6 Outgoing: CEDAR-N (Please Add Your Name Here)

H6: RD42 (Please Add Your Name Here)

H8: SND@LHC Hcal (Marco.Dallavalle@cern.ch)

Many thanks to QFIB colleagues that agreed to run at lower intensities for allowing SND@LHC to take data. The radiation monitor just outside the control room would go off with more than 10^5 particles/spill.
Many thanks to Maarten Van Dijk and colleagues that prepared and tuned the beam for ~5x10^4 particles/spill, and organized for a test yesterday evening, allowing for the beam reaching our detector.

On the bright side, the radiation monitor did not complain.
Unfortunately our DAQ does not stand the high rate and collapses after a few minutes.
However it was enough for collecting some sizable amount of data at 180 GeV; we failed at 140 GeV. This allow us to check the beam alignment.

We are making modifications to the DAQ but we do not know what our limit is. Past test beams worked at a few KHz. We would be grateful to collect 180 and 140 (and 100?) GeV data.

Thanks all concerned experiments for accepting the change in beam polarity next week.

 

H8: QFib (Suat Ozkorucuklu)

As parasitic user last week, we had set up our test system, align and took some data with 180GeV/c pions.

H8: STRAW TRACKER RD (Please Add Your Name Here)

H8: CMS RPC (Please Add Your Name Here)

AOB

Minutes by the respective speakers, edited by E. B. Holzer and M. Schwinzerl