FCC Cost & Schedule Study - ILF Zurich Meeting
Tuesday 8 August 2023 -
08:30
Monday 7 August 2023
Tuesday 8 August 2023
08:30
Agenda
Agenda
08:30 - 16:00
• A review of the construction schedule, including possible ways to reduce the schedule by about 6 months for each sector. • The calculation of contractor’s profit. • Possible alternative technical solutions such as permanent shotcrete for some areas of the underground. • Consequence of constructing only two experiment caverns. • Future collaboration between CERN and ILF. • Use of TILOS and reporting features of TILOS.