- ERAM-46,47,48 (last 3 ERAM) production is on-going
- status of ERAM-38-45
- ERAM-38 : at cabling division (6 dead pads)
- ERAM-39 : scanned OK
- ERAM-40 : mesh pulsing OK, Glued. scan is on-going.
- ERAM-41 : scanned OK
- ERAM-42 : 2-3 pads connected to each other. 10 rms noise spread over the surface (58 pads). To understand before gluing.
- ERAM-43 : mesh pulsing done, OK (no dead pad). glued, ready for scan.
- ERAM-44 : mesh pulsing done
- ERAM-45 : mesh pulsin done
- 3 stiffener remaining for ERAM-44 & 45. One to be sandblasted.
- Production of 6 stiffener (external company) : paused because the O-ring groove is not in the production drawings !
- Fabrizio is awaiting feedback from henry (IFJPAN)
- Charlotte will try to get the groove measured by CERN metrology : given today.