WP12 and contributions to HL-LHC Meeting #83
Thursday 24 October 2024 -
09:00
Monday 21 October 2024
Tuesday 22 October 2024
Wednesday 23 October 2024
Thursday 24 October 2024
09:00
News from the project
-
Vincent Baglin
(
CERN
)
News from the project
Vincent Baglin
(
CERN
)
09:00 - 09:15
Room: 112/R-028
09:15
Arcs, SAM and RT vacuum sector installation/commissioning procedures for LS3
-
Giuseppe Bregliozzi
(
CERN
)
Arcs, SAM and RT vacuum sector installation/commissioning procedures for LS3
Giuseppe Bregliozzi
(
CERN
)
09:15 - 09:30
Room: 112/R-028
09:30
Insulation vacuum installation/commissioning procedures for LS3
-
Jaime Perez Espinos
(
CERN
)
Insulation vacuum installation/commissioning procedures for LS3
Jaime Perez Espinos
(
CERN
)
09:30 - 09:45
Room: 112/R-028
09:45
Interconnections installation / commissioning procedures for LS3
-
Marco Morrone
(
CERN
)
Interconnections installation / commissioning procedures for LS3
Marco Morrone
(
CERN
)
09:45 - 10:00
Room: 112/R-028
10:00
RF and Impedance of HL and LHC warm modules: any limitations around the ring?
-
Patrick Krkotic
RF and Impedance of HL and LHC warm modules: any limitations around the ring?
Patrick Krkotic
10:00 - 10:15
Room: 112/R-028
10:15
AOB: Experiment cables sumary
-
Gregory Pigny
(
CERN
)
AOB: Experiment cables sumary
Gregory Pigny
(
CERN
)
10:15 - 10:25
Room: 112/R-028
10:25
Tour de Table
Tour de Table
10:25 - 10:35
Room: 112/R-028