WP12 and contributions to HL-LHC Meeting #84
Thursday 21 Nov 2024, 09:00
→
11:00
Europe/Zurich
112/R-028 (CERN)
112/R-028
CERN
38
Show room on map
Vincent Baglin
(
CERN
)
Description
Link to EDMS:
https://edms.cern.ch/document/2977230
Giuseppe Bregliozzi
giuseppe.bregliozzi@cern.ch
79789
162517
1
News from the project
Speaker
:
Vincent Baglin
(
CERN
)
HL news
2
AOB: Beam screen production and insertion schedule for 2025
Speaker
:
Cedric Garion
(
CERN
)
AOB: Beam screen production and insertion schedule for 2025
3
Warm bellows production: status, issues and actions
Speaker
:
Jan Hansen
(
CERN
)
warm bellows
4
In-situ coating installation / commissioning procedures for LS3
Speaker
:
Bernard Henrist
(
CERN
)
In-situ coating installation / commissioning procedures for LS3
5
ATLAS & CMS installation / commissioning procedures for LS3
Speaker
:
Josef Sestak
(
CERN
)
6
Readiness for IT String interconnection
Speaker
:
Willemjan Maan
(
CERN
)
Readiness for IT String interconnection
7
AOB: Non-conformities of beam screen parts at vacuum acceptance tests, what could be improved ?
Speaker
:
Cesar Vazquez Pelaez
(
CERN
)
EDMS 3195330
8
Tour de Table