-- Job processing: CMS MC production activities are switching to a new production round, hence a ramp-down occurred last week.
-- Data transfers: last week was week-4 of the CMS LoadTest07 (see [*]) with focus on T0-T1 routes. All issues found in week-1/2 were addressed and fixed in week-3, and operations were quite smooth in week-4. Not all T1's participated though (ASGC just finished migration to Castor-2, RAL was down due to Castor-2), and not all participating T1's move data all at the same time, but a quite constant aggregate transfer rate out of CERN was seen in most days of the week (see Gridview). A stop on thursday noon time (CET) was seen, probably due to disturbances to some services after network interventions. Next week CMS will restart the LoadTest with T0-T1 transfers, in the multi-VO scenario, and will additionally test selected T1-T2 routes.
-- Other preparation activities: as from the planning, a first working prototype of the set of CMS-specific tests within the SAM infrastructure is in place.
[*] http://www.cnaf.infn.it/~dbonacorsi/LoadTest07.htm
Speaker:
Mr
Daniele Bonacorsi
(CNAF-INFN BOLOGNA, ITALY)