Class A Labs
- Scaffolding to be assembled with grass hill access, for roof work, during ISOLDE stop -> June 12th - 13th
- Cooling upgrades planned, with ventilation cut, week 26 -> June 24th - 28th
- Door maitenance to be coordinated...found some random people wandering around b.179 yesterday who didnt realise coordination was required
MEDICIS
- #847M → Irradiation direct 1.6E18 poT received.
- THIS WEEK
- Opening of bunker S3 for EN-EL inspection for pulling a new cable betwen the bunker and the HV room during (E)YETS 24-25
- #847M on FE and start of collection of Ra-225:
- 1 MBq requested by IRA, CHUV.
- aiming for 100 MBq for NPL, UK.
- MELISSA RAMAN LASER: not operational for this week, need to purchase new mirors.
- Thursday morning
- 08:30 am : irradiation of new #834M (Ta - back of the line) between thursday and Friday as direct followed by indirect over the week-end (through UCx target).
- Change of trolley on friday 11 am