- GGUS:165529:
- T0-T1 test repetition (RAL-LCG2); in progress.
- Queries have been addressed by RAL.
- The tests are done and documented. What's next for this ticket?
- All the T1 GGUS tickets are still there, none of them has been closed.
- Reminder – T1 written reports on DC24: sites should submit the reports to DOMA. The deadline is 26 April 2024.
- Upcoming downtime @QMUL during 24-29 May.
- Power testing work in the building that houses QMUL cluster. In addition, some network work and tests of the cluster power off and on procedure will be carried out.
- Good time to point satellite sites to new homes before the main down time in July/August: RHUL, IC, Brunel, SUSX, OX to RAL.