PS-SPS Users Meeting for Week 14 held on April 4th, 2024

The agenda for this meeting is based upon user schedule v1.0.1, please cf. here.

News from the PS & SPS Physics Coordinator (E.B. Holzer, M. Jaekel)

Planning:

Very high overbooking, in particular at the end of the proton run
–> Even if the run get’s extended not all the requested beam time can be scheduled !
–> Users scheduled in parallel are often not fully compatible - requiring to operate in ‘time share’ mode!
–> Consider taking one of the available slots in the first half of 2024!
–> The slots which are currenlty marked as DRAFT in v1.1.0 are very likely to be moved by several (order of 5) weeks.

News from the Facilities Operations Meeting (FOM) (M. Jaekel)

Injector chain - Rough week with several stops. See PS/SPS presentations.
Friday 2 electrical pertubations. Cryo lost at point 6, beam stop for PS/SPS.

PS Machine Report (Ewen Hamish Maclean)

Challenging week due to various issues, but okay availability achieved considering (89%)

SPS Machine Report (F. Velotti, P. Arrutia)

Safety / Radiation Protection (Please Put Your Name Here)

nToF (M.Bacak and P.M.Milazzo)

TOF and EAST parasitic beam settings at standard physics beam conditions.
Intervention in NEAR and detector calibrations with several sources during the PSB stop on 03/04.
Data taking proceed as scheduled in all experimental areas.

East Area Beam Status (L. Nevay)

T09: Normal operation. Today will switch to electron beams. No issues.
T10: Normal operation.
T11: Off, no user.

East Area Users Tour de Table

T8 Main: IRRAD/CHARM (F. Ravotti / S. Fiore)

Normal operation. Despite issues at PS, quite good week (cumulated >2.5e16 p/w on T8, see plot below) thanks to the new high-intensity EAST_T8 spill. Access on Wednesday adjusted to match the whole day PS beam stop. In IRRAD, exchanged the dosimetry for the experiments started before Easter (iFAST, TE-MSC) weekeknd. For CHARM, BE-CEM components test continue and installed ATLAS and R2E experiments in the target area. We run until next Wednesday.

T9 Main: SHiP (Annika Hollnagel)

Link to PS East Area T9/T10 Beamline Meeting 2024-03-06 (slides):
https://indico.cern.ch/event/1387993/contributions/5835292/attachments/2813737/4911523/2024-04-06_ship-sbt_hollnagel.pdf

Easter week:

detector setup DAQ

Monday 2024-04-01:

tilt ‘ladder’ temporary fix

A few more days of beamtime left:

T9 Incoming Main: CMS BRIL - Week 15 (Olena Karacheban)

We have a confirmation that we will have the telescope for the test beam. We will need to crane it in the T9 area together with DESY table.
We summarized our primary beam needs to PS coordinators.
We are cheching if the nitgogen disctibution with 10 mm pipe can be connected to our setup, which uses 6 mm pipe.
We filled in safety form.
We will be in toch with Dipanwita for planning of the first day.

For the telescope (Andre Rummler): telescope with exception of planes, fei4 and PI stage was stored in the east area. Other equipment was put into TREC and will be brought over by self transport.

T10 Main: ALICE ITS3 (Paolo Martinengo)

Smooth data taking, took data also during Easter and plan to continue

T10 Incoming Parallel: ALICE FoCal - Week 15 (reported by Paolo)

CANCELED - they will not join as parallel user in week 15


North Area Beam Status (L. Nevay)

General: Beam commissioning in progress.

H2: Commissioning almost completed. H2-VLE not yet comissioned, tentatively planned for week 16 tbc with SY/BI and only if no user wants the beam.

H4: Comissioning almost completed, H4-VLE XCETs still to be validated by SY/BI. Beam to be handed over to RD51/GIF++ on Tuesday 09.04.

H6: Commissioning almost done. Electron and positron beams being prepared today.

H8: Commissioning proceeding well, steering and focusing complete for main 180 GeV/c beam.

M2: Hadron and muon beam commissioned. Cedar commissioning ongoing. Preliminary scans look good. Some issues still with the FISCs that is being checked with BI.

P42/K12: Beam commissioning basically done, waiting for feedback from NA62.

North Area Users Tour de Table

M2:

Incoming Main: AMBER - Week 15 (Thomas Pöschl)

P42-K12:

Incoming Main: NA62 - Week 15 (Roberto Piandani)

Apology to missed the meeting, I had problems at the experiment.
Most detectors are ready for the start of the data taking, during the week end we agreed with Johannes to have muon beam needed for calibration of detector.
Next week, we have to understand exactly when, we will fill the CEDAR with Hydrogen.

H2:

Incoming Main: LHCb - Week 15 (Ettore Zaffaroni)

The detector is ready to be installed next week.
Beam: electrons between 10 and 300 GeV, as wide as possible, rate up to 100k particles per spill.
No strong requirement on purity, momentum spread <10%
Some runs with muons for alignment.
ISIEC has been sent.

H4:

Incoming Main: RD51 / DRD1 - Week 15 (Alessandro Ferretti, Roberto Guida, Giuseppe Iaselli, Eraldo Oliveri, Yorgos Tsipolitis)

Groups:
SETUP A, B: PICOSEC (F. Brunbauer, M. Lisowska)
SETUP C: STRAW (T. Enik, K. Kuznetsova)
SETUP D: RHUM (M. Iodice, G. Sekhniaidze)
SETUP E: TWIN TPC (F. Garcia Fuentes)
SETUP F: GDD/RD51 Tracker (K. Floethner)
SETUP G: USTC (Y. Zhou)
SETUP H: CMS ME0 (A. Pellecchia, P. Everaerts)

Beam: Mostly high rate muons, few pions shifts, NO Goliath

Installation and operation

Incoming Parallel: GIF++ - Week 15 (Please Put Your Name Here)

H6:

Incoming Main: ATLAS ITK PIXEL - Week 15 (Andre Rummler)

Currently we are extremely low on person power for the first weeks and also there are issues with the materials necessary to operate three telescopes at once this week (H6A, H6B, T9). We might only start a few days later or even in week 16 but we are trying hard to make it possible.

H8:

No main user, incoming parasitic user (see below)


Parasitic Users

H4 Incoming: STRAW TRACKER RD - Week 15 (Temur Enik, Katerina Kuznetsova)

H6 Incoming: CMS MTD ETL - Week 15 (Iván Vila)

Main goal:

Intermediate milestones:

Current Readiness:

Telescope readiness (Andre Rummler): System is set up although depending on the choices we might still dismount some telescope planes / the FEI4.

H8 Incoming: LHCb - Week 15 (Federico Ronchetti)

Possibility to install for SciFi testing.
The detector is not ready yet and should still be transported from Lausanne.
Check with Maarten.


AoB

Minutes by the respective speakers, edited by E. B. Holzer, M. Jaekel, T. Shulha, and M. Schwinzerl