FCCee beam transfer meeting #8 : special integration

Europe/Zurich

Participants: Y. Dutheil, P. Trubacova, F. Valchkova-Georgieva, S. Yue

  • Files exchange between ABT and Fani
    • files OK
    • minor issue with boster extraction >1km, for next exchanges need to cut line in 2 with 1 point overlap
  • Integration model in PB
    • list of points received by Fani and added in the PB integration model
    • Fani presently adding all the space reservation for 
    • control of the position of the dumps confirmed their correct placements
  • Question of alcove placement
    • minimum distance between entrance of alcove and beamline is 15m
    • Pavlina will present shortly the ABT requirement on 15/05 at the integration meeting.
There are minutes attached to this event. Show them.
    • 15:00 15:20
      discusstion 20m
      Speaker: Sen Yue
      • Intergration shows that the horizontal shift of beam in collider dump system is ~5.1 m
      • there maybe a larger requirement on alcove space
        • the alcove number is undetermined
        • the distance between alcove and beam is ~ 15m