PS-SPS Users Meeting for Week 22 held on May 30th, 2024

Physics Coordination schedule:

June 13th: User meeting exceptionally on zoom only (for availability of the conference room).

News from the PS & SPS Physics Coordinator

E.B. Holzer, M.R. Jäkel

Today 30.05 : SPS Magnet exchange on Thursday, no beam from Thursday 8h00 to Friday late morning

Proton Run 2024

Ion Run 2024

Reminder: Beam time exceeding the limits of 2 weeks PS beam time and 1 week SPS beam time (added proton and ion beam time!) per year need the approval of one of these CERN committees: SPSC, LHCC, DRDC, INTC, RB or IEFC. Consider joining a DRD collaboration, if you require more beam time.

News from the Facilities Operations Meeting (FOM) (M.R. Jäkel)

Upcomming MDs:

Upcoming Techncial Stop

PS Machine Report (Denis Cotte)

SPS Machine Report (Stephane Cettour cave)

Plan for the week and next


Safety (A. Schouten)

nToF (M.Bacak and P.M.Milazzo)

Data taking on:

Few issues due to elecrical instabilities on 26.05.
HpGe detector in NEAR has changed and activation measurement will restart tomorrow (31.05).

Beam in standard conditions.


East Area Beam Status (M. van Dijk)

T09: Good operation. No major issues.
T10: Mostly good operation, some issues with magnet T10.BHZ.027, addressed by experts, should be more stable now.
T11: No operation.

East Area Users Tour de Table

T8 Main: IRRAD/CHARM (S. Fiore / F. Ravotti)

Regular user operation. Good week: cumulated ~2.8e16 p/w and reached CHARM TID target, see plot below. We reduced the intensity on Monday morning to test cool-down scheme for CHARM. Data being evaluated to decide how to proceed next week. Beam centering very good (center within +/- 2mm >92% of the time).

Access during Wednesday morning. In IRRAD exchanged samples for TE-MSC experiment, and irradiations for ATLAS-HGDT performed over the week. All other long-term experiments continue. In CHARM full rack swap with new setups by CMS and BE-CEM. We continue until next Wednesday. On Tuesday morning after 9am, planning some hours of beam steering and measurement with Marc/Eliott.

T9 Main: VLAST (LI Xiang)

The beam availability is very good. The magnet was down for a few times but fixed by experts soon.
Gamma-ray is an important observation object for VLAST (Very Large Area gamma-ray Space Telescope). And we have been carrying up several tasks:

  1. Calorimeter calibration with muons;
  2. Electron beam taking from 1 to 5 GeV;
  3. User magnet calibration with electrons and muons;
  4. Gamma-ray (induced by electron) data taking.

A few figures from our analyses:

  1. User magnet calibration

  2. Gamma-rays from electron beam

We are still accumulating the statistics.
Thank you for the good beam, and thanks to Dipanwita for the beamfiles.

T9 Incoming Main: E+BOOST - Week 23 (S. Carsi)

Installation

Sketch of setup layout

What is needed from the CERN Staff

Measurement plan

Once the setup in installed, we will

Thanks

A special thanks to all the CERN Staff, especially to Dipanwita and Aboubakr for their kindness and availability to find the best solutions for us.

T10 Main: EIC dRICH (Please Put Your name here)

T10 Incoming Main: ALICE ITS3 - Week 23 (Paolo Martinengo)

preparing set-up in the lab, no special needs/requests

T10 Incoming Parallel: ALICE FOCAL - Week 23 (Please put your name here)

User will not take beam during week 23.
TODO: update the schedule accordingly.


North Area Beam Status (M. van Dijk)

General:
H2: Smooth operation.
H4: Smooth operation.
H6: Good operation.
H8: Good operation, some access issues with patrol on PPE148, solution to be identified.
M2: The quad9 fluctuations are now corrected following an EPC intervention on Monday. Otherwise good operation.
P42/K12: Smooth operation. Patrol lost in ECN3, kind reminder to be careful because the re-patrol involves a lot of persons and corresponds to time lost.

AWAKE (M. Bergamaschi)

  M T W Th F S S M T W Th
SPS extractions 332 789 MD MD 706 810 707 826 484 MD Stop
Hours of beam to AWAKE extraction 2.1 6.5 MD MD 5.9 5.0 4.6 6.5 3.6 MD Stop
Hours of interuption during AWAKE extractions 0.3 2.1 MD MD 2.9 3.6 0.0 0.6 0.5 MD Stop

Detailed program:

North Area Users Tour de Table

P42-K12:

NA62 (Phil Rubin)

We enjoyed a very productive weekend, thanks to a remarkably high accelerator duty factor and good beam quality, which unfortunately halted with the leak detection access. We lost 4 hours this morning after a fault in a K12 bend magnet. We are presently in standby mode, with some detector voltages off. We will patrol and close access to the area this evening and patrol the area in the morning.

We believe we have isolated and mitigated the source of noise in our trigger system which has caused us to lose ~2% of events that otherwise pass all our trigger requirements.

M2:

Main: AMBER (Thomas Poschl)

H2:

Outgoing Main: ALICE FOCAL (T.Isidori, R.Simeonov)

Incoming Main: ILC DUMPS (M. Tisi)

H4:

Main: NA64e (L. Molina Bueno)

We continue data taking and we collected up to now 3.3x10^11 EOT

H6:

Outgoing Main: EP PIXEL (Dominik Dannheim)

Main: CMS PIXEL (Branislav Ristic)

Parallel: ATLAS HGTD (Stefano Manzoni)

Testing ASIC+LGAd hybrid modules and LGAD Sensors alone for HGTD Phase II upgrade

Kept the same steup - safety done

Same beam setup as last weeks, maybe we will test slightly higher rate if possible (x1.5-x2) in the first week

There is still a glitch in the published scheduled with two main users in week 22, we will update the schedule ASAP.

Incoming Main: AIDINNOVA WP6 - Week 23 (Please put your name here)

H8:

Main: ATLAS TILECAL (G.Usai and T.Mkrtchyan)

We have a 2W beam time dedicated to testing of phase II upgrade electronics, in particular components going to the FDR this year:
–the daughterboard (on detector optical data transmission board)
–Preprocessor (off detector)
We have a full slice of the phase-II system and also a slice of the legacy system so we can study all aspect related to calibration of the upgrade system.

During the week we had several issues with the setup and we were not able to take much data.
—small mechanical failure in the encoding of the table position was fixed with the help of ATLAS technical coordination
— A cooling leak in one of the module force us to dismount clean and remount all ondetector upgrade electronics.

Picture show the condensation over the cooling body of the SD. Fortunatelly this result in only a minor failure in one of the HV disctribution boards.

-We were able to re-start electron data program yesterday evening, Thanks to Maarteen for the prompt tuning of the beam.

Incoming Main: ATLAS MICROMEGAS (R. Hertenberger, V. D’Amico - LMU)

Test of ATLAS Micromegas Series Production Chamber
H8B PPE 158 behind the magnet
start 5.6.2024 end 19.6.2024
180 GeV/c pions, x times 100 k per spill with x = 1 … 9
beam should be as parallel as possible
setup: 2 upstream reference detectors with 2 trigger scintillators
1 Micromegas to be tested
2 downstream reference detectors
gas: Ar:CO2:C4H10 93:5:2 Vol% at environmental pressure
2 50 l bottles are available
piping and gas system will be prepared by us
we need craning of 2 concrete blocks, DESY table, 3 detetor elements, 1 rack
safety inspection is scheduled for 5.6.2024 17h

Incoming Parallel: MEDIPIX (Benedikt Bergmann)

Parasitic Users

Outgoing H6: MONOLITH (Please Put Your Name Here)

H6: RE1 AMS L0 (M. Duranti - INFN Perugia)

H6: ATLAS MALTA (Please Put Your Name Here)

H8: STRAW TRACKER RD (Please Put Your Name Here)


AoB

Minutes by the respective speakers, edited by E. B. Holzer, M. Jäkel, T. Shulha, and M. Schwinzerl