NA CONS monthly meeting - follow up #5
● Moteur et embrayage
LAST MEETING:
- motors offer will come (confirmed by manufacturer)
- gearbox offer to followup (Morad: after return from CAS so far no answer)
- 37 motors + gearboxes needed, for NACONS for the LS3 installation there is only ±10 needed
- USA material, but probably ordered by EU representative so we avoid non-EU purchase
Morad informs, that some gearbox types are available in radiospares. Option to buy what they have and check conformity.
Federico: We should ask more money on NACONS for 2025 (either add to running project, or ask as a new contribution)
For the motors + gearbox we wait until Morad gets full price offer
ACTIONS TO BE RESOLVED FOR TODAY'S MEETING:
TODO David: clarify with Federico whether money requested (already)
TODO David: clarify with Federico whether a BIFT presentation should be made by operators for installations not needing movable parts
TODO Morad: get completed offer for motors + gearboxes
● Design Flex
Aurelie: we might be able to use short radiation tolerant cables, SHV radhard connectors are needed on patchbox.
Michel: High voltage bias goes through one of the pins in 2x SUBD 26 high density connectors. Signals are connected by crimping. This is standard done in ISOLDE and we'll re-copy to the new installations.
Chiara: Control 1+2 will be done in ML. First done by Ben or William, second by Morad or Christophe). The third control will be in PM section, either David or Michel.
TODO Lucas: present on the next meeting already available 3D models
● BSI Et BSP à remplacer au prochain YETS
Christophe confirms, that all foils are the titanium version. Confirms as well that all the tanks are available.
● Integration
- There are some naming conventions to change due to changes in installation. The new names are proposed in 'Secondary Emission Monitors (SEM) activities for the SPS NA CONS Part 1 project' specification, soon to be released.
- Aurelie points out criticality of contacting integration team as on some locations we'll need more than just changing the name. Christophe informs that there are 2 locations, where is no space for additional BSG and we will need to discuss with integration how to deal it - either change position of BSG, or move magnet to make a space.
TODO Aurelie: contact F. Galieazzi and/or Sylvain Girod to start discussion of the integration. Christophe provides necessary info to Aurelie for follow up on integration.
● ECRs
Aurelie proposes the document 'Secondary Emission Monitors (SEM) activities for the SPS NA CONS Part 1 project', currently circulating in overleaf, to be released.
TODO David: Add MIchel, Lucas, Morad as co-authors
TODO Aurelie: release the document
● Grilles à produire
Foreseen to be produced for LS3:
◦ BSG.210350 (proto)
◦ 3 BSG P42
◦ 3 BSG TT20, TT21, TT23
◦ 3 BSG TBIU
◦ 4 BSP to BSG -> TT24
(everybody agrees)
TODO Morad: contact P. Frichot to produce grids of 0.5mm (P42), if success we go with this solution, if not there are old grid in stock, which can be used.
TODO All, next meeting: discuss if option using wires is possible for grid 0.5mm as a last resort