- Schedule update
- Global schedule
- 7/1-- Launch "Our shift system" for Fuji B4.
- 7/16-- Launch Bare PCB QC for production in our current estimate - fingers-crossed.
- Two task lines for the weeks of 7/1 and 7/8.
(1) Reception QC line: Populated PCB QC after HV/LV-setup fix (to be assembled with ITkPixv2)
(2) V2 module assembly QC and R&D line: ITkPixv2-related QC after PC fix (for core column issue)
- Shift update accordingly
- For the weeks of 7/1 and 7/8: As scheduled for Mon-Wed. If the existing components are all tested, may cancel shifts for Thu-Fri.
- From the week of 7/16: Further updates to be informed by 7/8 at latest.
- Details in the shift table
- Items to be sorted out before production
- Items in red needs immediate actions
- Items in orange should be addressed next week
- Initial list with our actions & priorities in the spreadsheet. More to be added via further rehearsal by several people from next week.
- Metrology machine scan speed up in BM QC
- Initial implementation already done by Sugawara san -> BM Flatness+height 38->16min.
- Mitigation proposals were presented by Aoki san, also considering which variables are stored in DB.
- Some of the proposals will be tried next week, while keeping the necessary presicions.
- HV/LV automation
- Ikegami san already established window-based system with several updates e.g. catch the connection error first and apply HV/LV automatically.
- Kumayama will address to update the output-line format in result csv file.
- Next meeting next week or maybe in two weeks