- Intermittent problems over the last 30 days.
- Various instabilities at some sites and issues that we will discuss.
- The EL9 update drags on and on.
- AGLT2 MSU still having problems with getting the officuak RHEL9 install to work.
- MWT2 Illinois will move to a new building and when the servers come back they will be running RHEL9
- SWT2 OU Updates done but still using an CentOS 7 container.
- SWT2 CPB so close but not yet there/
- Next scheduled meeting on Dec 25 is canceled so will next meet on Jan 8.
- I will discuss with Eric to see if we can find a better schedule.