Proton Run 2024

Ion Run 2024

Reminder: Beam time exceeding the limits of 2 weeks PS beam time and 1 week SPS beam time per year need the approval of one of these CERN committees: SPSC, LHCC, DRDC, INTC, RB or IEFC. Consider joining a DRD collaboration, if you require more beam time.

News from the Facilities Operations Meeting (FOM) (E.B. Holzer)

Target intensities:

Upcoming SPS MDs next weeks :

https://be-dep-ea.web.cern.ch/content/md-planning-north-area
Dedicated SPS MDs - if not anounced differently - are taking place from 8:00 to 18:00

PS Machine Report (Alex Huschauer)

Excellent availability of 98.1%.

Main issues

Status of beams

SPS Machine Report (Michael Schenk)

Safety (A. Schouten)

nToF (Michael Bacak and Paolo M Milazzo)

Smooth data taking in all experimental areas.

EAR1: last days of the 63Cu(n, g) measurements, from Monday 12.08 start of the 238U(n, g) campaign. No need for changes in the experimental set-up.
EAR2: 88Zr(n, g) measurement. Isotopic production has been provided at Los Alamos laboratories and sent to PSI where the sample will be prepared. Then, the sample will be directly placed on beam on 16.08.
In the meanwhile auxiliary measurements are running for normalization, evaluation of the background and detector calibrations.
NEAR: activation measurements

Protons received in standard conditions

East Area Beam Status (M. Van Dijk)

On call number: 67500

T09: Good operation.
T10: Good operation.
T11: P349 installation underway.

East Area Users Tour de Table

T8 Main: IRRAD/CHARM (F. Ravotti / S. Fiore)

Very good week in T8, protons reached 2.82E16.

T8 transmission optimized at the beginning of the week (see plot below).

In IRRAD we finished with the EP-DT-DD R&D (DRD3) experiment and continuing with long-term experiments (TE-MSC, EN-MME).

In CHARM no testing last week as per user request. Yesterday new setup for ATLAS mounted, CMS and BE-CEM-EPR modified

T9 Main: STCF ECAL&PID (Yunlong Zhang)

The detectors were installed in T9.
The beam has worked well. We have used the muons, e, hadrons to test.

Detectors:

Claorimeter:
muons:

e+:

PID:

tracker

T9 Incoming Main: NP06 ENUBET (Week 33) (Valerio Mascagna)

T10 Main: ALICE ITS3 (Paolo Martinengo)

Data taking successful, we are happy and preparing for next slot

T10 Main: EIC BARREL ECAL (Hwidong Yoo)

T10 Incoming Main: ALICE TOF (Week 33) (Yongwook BAEK)

- Test xy-2D readout MRPC
- HV scan, position scan
- Use standard mixture & eco gas

T11 No beam + Incoming Main: P349 (Week 33) (Vincent Verhoeven)


North Area Beam Status (M. Van Dijk)

On call number: 67500

Target intensities

Original plan

T2 T4 T10 T6 from
30 75-85 55 30 02.08.
30 42 21 30 12.08.

New plan

T2 T4 T10 T6 from
30 100 52 30 08.08.
30 42 21 30 19.08.

H2: Good operation.
H4: Good operation.
H6: Good operation with higher rate last week. Thanks to EP PIXEL for sparing an hour or so for some optics checks and measurements.
H8: Mostly good operation, failure of beam stopper XTDV.042.572 (between H8B and H8C) leading to some difficulty. Can operate in mode dependent on PPE158 (access isimultaneous with PPE168) or always closed (no beam in PPE168) but changing it takes quite some work. For now closed on request of DRD6 IDEA DRC. Repair expected to require ~2 days.
P42 / K12: Major issue with P42 XTAX, causing 20 h of downtime to NA62. Mitigation found and way forward to be discussed further. Access via TCC8 access point requires stop of full North Area. Went to beam dump mode yesterday, including increase of T4 intensity to 100 units.
M2: Good operation. Issues with the 2nd MBPL magnet for NA64mu with cooling and power converter which was fixed.

HIRADMAT (Please Put Your Name Here)

North Area Users Tour de Table

P42-K12:

NA62 (Week 33) (Joel Swallow)

M2:

Main: NA64mu (L. Molina Bueno)

A brief summary is updated to the Indico. We resume our activities after the long stop that lasted until Friday in the end. Saturday we finish calibrations and set up our trigger and Sunday evening we manage to start data taking. We lost other shift on Tuesday due to a problem with the cooling of the MBPL magnet used in MS2. We adjust the beam on Tuesday after the magnet was repaired with Dipanwita and we are currently recording data.

H2:

Outgoing Main: CMS HGCAL (Chiara Amendola)

Thanks to everyone for the support!

Main: CMS HF (Alexi Mestvirishvili)

Started installing our setup August 7th, transition from HGCAL to HF was very smooth!
Beam is greit. We are busy with alignment and then we will be asking Nichos to help in beam adjustment, but overall beam is perfect
! our beam counters

We saw first signals from SiPMs 

Incoming Main: TECHNO CLS (Week 33) (Stefano Carsi)

Experimental sketch

H4:

Main: NP04 (Christos Touramanis)

Smooth data taking since beam became available last Friday.
Detector stable, nothing special to report.
Continuing over the rest of our run.

H6:

Outgoing Parallel: ATLAS ITK PIXEL (Andre Rummler)

Little progress on communication problems with ITkPixV2 quad due to lack of person power. Setup dismantled and removed by 1100 and prepared for HGTD (TLU2, FE-I4 retune, etc.).

Outgoing Main: EP PIXEL (Dominik Dannheim)

Main: ATLAS HGTD (Stefano Manzoni)

Sorry but I am not able to connect because we are running a test right now.

Two weeks of testbeam started yesterday: main goal is measuring hybrids (ASIC+LGADS) performances before and after irradiation.

H8:

Outgoing Parallel: LHCB (L. Martinazzoli)

Successful week of data taking for the LHCb VELO TimePix group.

Thanks to Maarten (and all the beam experts) for the support!

Looking forward to being back in weeks 42-43!

Outgoing Main: CMS PPS (F. Garcia)

This week as Main user was interesting. The start was difficult, however during the period things converged slowly and the physics program was almost completed.

The beam characteristics were as requested, however once the all the setups upstream were installed the beam was broadened on both planes as we expected however larger than what we wished. In the H8C area turns out to be very difficult to have a narrow beam and this is a fact.

The Beam physicst have done all possible to satisfied our requirements in terms of the beam characteristics and we got a good one. The intensity was varied during the whole week, stating with 17k/spill then 37k then again beack to 17k and last day 147k (the best).

The Diamond detectors were tested with different types of LED diodes: Red, Green and Blue. We expect for the next test beam to test Yellow and white.

The data analysis is ongoing…

Actions requested:

For what was formelly known as the TOTEM CR, we would need to a repairment of the beam control computer H8C2 and for the H8C3 the second monitor/TV to be replaced.

All the team would like to thank to all the crews in the NA. Everyone was reachable and their actions were taken just after reporting them, even during the weekend.

Main: QFIB (Please Put Your Name Here)

Parallel + Incoming Main: DRD6 IDEA DRC (Week 33) (Seungkyu, Gabriella)

DRD6 IDEA DRC Korean team and EU team are working togheter.

Parasitic Users

H6: ATLAS MALTA (Please Put Your Name Here)

H6 Incoming: CMS MTD ETL (Week 33) (Please Put Your Name Here)

H8: STRAW TRACKER RD (Please Put Your Name Here)

H8: QFIB (Please Put Your Name Here)


AoB

Minutes by the respective speakers, edited by E. B. Holzer, M. Jäkel, T. Shulha, and M. Schwinzerl