Present : D. Budker, Y. Dutheil, D. Gamba, W. Krasny, W. Placzek
- SRR and ECR
- The SRR (space reservation request) aims at reserving the area of the SPS and TI18 tunnel
- The ECR aims at detailing the installation of the pillar on the SPS tunnel which will allow the transport of the primary laser from the TI18 tunnel
- The penetration between TI18 and SPS tunnels already exists and its size is compatible with the PoP laser transfer line
- Gamma factory contribution to the ESPP input
- European Strategy for Particle Physics is a CERN process which is presently gathering request and a summary document is presently being written with a small contribution from PBC
- Another document summarizing in more details all the studies conducted for the gamma factory
- The gamma factory contribution needs to match the request context and format of the ESPP but difficult exercise due to the very broad prospects of the GF project