Thanks to everyone for getting in their WBS 2.3 quarterly reports.
WBS 2.3 top-level quarterly should be done soon.
WLCG/HSF meeting coming up in early May
Tier-2s need to work on finalizing procurement and ops plans (discuss in WBS 2.3.2)
- After procurement plans are ready, we need to work on 5-year estimator
Milestone updates still needed for WBS 2.3 https://docs.google.com/spreadsheets/d/1Y0-KdvsRVCXYGd2t-SqCEFlppZn_PjvUUVDGp2vJjc4/edit?gid=1906829311#gid=1906829311
- #117 Feb 2025 Delayed (by SWT2) Updates? WLCG site network monitoring 2 years delayed so far...
- #374 Apr 2025 On Schedule (waiting on BNL?) Need updated comment?
- #279 Apr 2025 Delayed Need updated comment? Tier-1
- #392 Jan 2025 "On Schedule" Needs update Tier-1
- #393 Jan 2025 "On Schedule" Needs update Tier-1
- #191 Apr 2025 Delayed Tier-1 Update comment?
- #310 Feb 2025 Delayed SWT2 update estimated date and comment
- #316 Mar 2025 Delayed SWT2 update estimated date and comment
- #363 Mar 2025 On Schedule update status or estimate date/comment
- #410 Apr 2025 Delayed WBS 2.3.4 update comment?
- #414 Apr 2025 On Schedule but is this a real milestone (WBS 2.3.4)
- #328 Apr 2025 Delayed WBS 2.3.5.1 see comment, update estimated date
- #415 Mar 2025 WBS 2.3.5.2 Update estimated date and comment OR retire?
- #416 Jun 2025 WBS 2.3.5.2 Is estimated date correct? Update comment?
- #419 Mar 2025 On schedule WBS 2.3.5.2 New estimated date needed. Change Status to Delayed
- #428 Mar 2025 Delayed WBS 2.3.5.3 New estimated date, update comment