Record of MBRD meeting minutes:

 

  • All coils apertures are complete but last 3 ones are left. It was decided to put on hold thise 3 apertures as they include biggest coils, waiting the LMBRD1 cold MM test results benchmarking  from April.
  • Growth of a2 harmonic is expected on those apertures with pairing big and small coils resulting in shift of mid plane.
  • MBRD3 assembly about to be completed
  • MBRD4 to be assembled till April 25.
  • ECR on swap of 50 microns QH insulation layer will be drafted by INFN
  • MBRD3 inspection by INFN this week including documentation check,
  • MBRD3 shipment from mid February to B180
  • MBRD4 APs in sleeves, WMM performed last week
  • SM18 test plan meeting being resumed with TM section from end January once draft is available according to last
  • Closing of NCRson MBRD3-VS06 being finalised with last INFN comments (EDMS 3087008)