HL MBRD Weekly meeting
→
Europe/Zurich
Record of MBRD meeting minutes:
- All coils apertures are complete but last 3 ones are left. It was decided to put on hold thise 3 apertures as they include biggest coils, waiting the LMBRD1 cold MM test results benchmarking from April.
- Growth of a2 harmonic is expected on those apertures with pairing big and small coils resulting in shift of mid plane.
- MBRD3 assembly about to be completed
- MBRD4 to be assembled till April 25.
- ECR on swap of 50 microns QH insulation layer will be drafted by INFN
- MBRD3 inspection by INFN this week including documentation check,
- MBRD3 shipment from mid February to B180
- MBRD4 APs in sleeves, WMM performed last week
- SM18 test plan meeting being resumed with TM section from end January once draft is available according to last
- Closing of NCRson MBRD3-VS06 being finalised with last INFN comments (EDMS 3087008)