• Good production for the last couple of weeks.
  • Good progress on EL9 updates.
    • AGLT2 MSU closer.
    • MWT2 Illinois finished on Jan 31.
    • CPB finished all servers except storage.
  • It looks like we are in generally good shape for software updates - see the services table: https://docs.google.com/spreadsheets/d/1_fKB6GckfODTzEvOgRJu9sazxICM_RN95y039DZHF7U
    • Sites using puppet got a nasty surprise a couple of weeks ago so there is one service item that is still an issue.
  • Subject to management approval the operations and procurement plans will be on March 31.
    • The funding levels are known for this year (subject DOGE effects).
  • We have a deadline of 28 Feb to provide estimates of how much money it will take to establish 400 G WAN connectivity by 2029 (i.e. for Run 4/HL-LHC).