Summary:

  1. Collette to check with Ben which ICT model to order depending on flange/aperture size requirements in e-lines.
  2. Collette to check how many ICTs required for 150 MeV line (at least one, requested by Steffen). 
  3. Integrate all additional ICTs into layout (Collette to organise with EN/ACE).
  4. If all fine, come back to Marek and Tom for the order from Bergoz (around 14 weeks delivery from Bergoz). 
  5. In parallel, cable request to be updated.