Discussion about possible ECAL/HCAL in 2026
-
-
08:00
→
08:20
Inputs for today's discussion 20mSpeakers: Hidetoshi Otono (Kyushu University (JP)), Zhen Hu (Tsinghua University (CN))
1. AHCAL Transportation Constraints
Overview:
-
The transportation team has provided the dimensional limits of the transport platform:
-
Width: 1000 mm
-
Length: 3000 mm
-
Height: 900 mm
-
-
The current AHCAL structure exceeds these limits slightly.
Options Discussed:
-
Larger Transport Platform:
-
Would require new design and verification by civil engineering.
-
Long lead time (previous example: 3 months).
-
Estimated cost over 10k CHF?
-
-
Rebuild the Frame:
-
The current frame holds 40 layers and is not disassemblable.
-
Remaking the frame would be costly and time-consuming.
-
-
Modify the Existing Frame:
-
Mechanical feasibility under investigation.
-
May involve reducing frame thickness or trimming corners.
-
Preliminary feedback suggests this is technically challenging.
-
Alternative Approach:
-
Custom Cradle:
-
Proposed to build a simpler cradle with lifting points 1.8 meters apart.
-
Should support the frame (without iron plates).
-
Target weight under 2 tons.
-
Could be manufactured locally in China to reduce cost.
-
Action Items:
-
Shunliang? to provide detailed photos of the frame and potential lifting points.
-
USTC mechanical engineers to evaluate the cradle design.
2. DAQ and Trigger System
TLU-Based Trigger Logic:
-
The TLU board accepts 6 inputs:
-
2 channels for veto scintillators
-
4 channels for analog signals from AHCAL
-
-
TLU settings (threshold, delay, veto stretch) can be adjusted via software.
-
No firmware update required.
-
Configuration validated during previous test beam campaigns.
Trigger Optimization (Presented by Yasuhiro Maruya):
-
Simulation tested conditions for neutron rejection and ν_eCC efficiency.
-
Trigger condition:
-
At least 2 of layers 18, 19, 38, or 39 receive signal > 0.2 MeV within 10 ns window.
-
-
Efficiency:
-
ν_eCC detection: ~98%
-
Good suppression of delayed neutron background.
-
Engineering Concerns:
-
Need to confirm where the sensitive region of AHCAL begins relative to the floor.
-
This affects placement height of veto scintillators.
Action Items:
-
Yunlong/Zhen to confirm sensitive region height with photos and measurements.
-
Brian to propose scintillator dimensions (suggested: 80x80 cm).
3. Digitization Updates (Yasuhiro Maruya)
Key Changes:
-
Implemented new digitization from Hongbin:
-
Cell-by-cell calibration of SiPM and electronics characteristics.
-
Consideration of low-gain saturation effects.
-
Artificial cap at 80 MeV per cell introduced for worst-case scenario.
-
Results:
-
ν_eCC Energy reconstruction:
-
Std. Dev. (E_reco/E_truth):
-
Old: 29%
-
Updated: 32%
-
With saturation: 35%
-
-
-
ν_eCC PID and background rejection:
-
Slight improvement with calibrated digitization.
-
Slight degradation with saturation, but within acceptable bounds.
-
Conclusion:
-
Digitization changes do not significantly impact overall detector performance.
4. D-Meson and Tau Decay Handling
Motivation:
-
GEANT4 does not fully simulate decay of charm hadrons and tau leptons.
-
Previously defaulted to hadronic decay only.
Updates:
-
Introduced Pythia8 decay handling.
-
Enabled more realistic decay chains including leptonic channels.
Effects:
-
ν_eCC PID rejection performance:
-
Slight drop (~8%) in ν_μCC and NC rejection due to muon tracks.
-
Minor effect on ν_eCC detection.
-
-
Flux measurement uncertainty:
-
Increased slightly (from 56%~112% to 57%~118%).
-
Conclusion:
-
No critical degradation.
-
Handling of D decays via Pythia8 is preferred for realism.
5. Miscellaneous and Next Steps
Photos and Geometry
-
Shunliang will visit the site and take photographs.
-
Frame geometry, lifting hook placements, and sensitive region locations will be documented.
Trigger Placement and Design
-
Scintillator placement depends on active volume height.
-
Placement should avoid interference and align with active area.
Summary:
-
Frame transportation challenge actively discussed.
-
DAQ and digitization components are mostly ready.
-
Trigger logic and placement design progressing.
Next Meeting Tasks:
-
Share frame photos and detailed geometry.
-
Finalize cradle/lifting structure design.
-
Confirm trigger logic parameters with hardware.
-
Validate decay model impact with further simulation if needed.
-
-
08:20
→
08:40
Simulation update 20mSpeaker: Yasuhiro Maruya (Institute of Science Tokyo (JP))
- 08:40 → 09:00
-
08:00
→
08:20