Introduction:

F. Pedrosa started the meeting announcing that this is the second of several HI-ECN3 WP7 focus meetings that will be organised, and this one specifically will be focus in Civil engineering and the two presentation that could not be delivered in the past meeting

 

Target Station

G. Humphreys presented the target station configuration as is with the different type of shielding, the load distribution (maximum load 45T/m2) and the concerns on having a pit just below the vacuum vessel. The pit is required by HSE-RP to increase the shielding below the target, but it is a challenge for the civil engineering team and a concern for the target station team. Most of the discussions during the presentation focused on the pit and the associated issues that could arrive. The same amount of shielding below the target cannot be achieved without the pit, otherwise the beam line would have to be raised and consequently the SHiP experiment.

From the presentation and the discussions, the following actions were defined:

 

Target complex service building

J.-L. Grenard presented an overview of the services building the floor load capacity requirements, the RP classification for the different areas of the building, the sump requirements, …

From the presentation and the discussions, the following actions were defined:

 

SHiP Experiment: 

P. Santos Diaz presented the preliminary civil engineering requirements for the SHiP project, highlighting updates on the layout drawings, building model integration, and infrastructure planning. The discussion covered service connection layouts between surface and underground levels, load constraints for equipment such as the muon shielding, straw tracker, and spectrometer magnet and drainage requirements for mineral oil-based systems. The need for a dedicated support structure for the He balloon and a potential liquid scintillator collection system was discussed. Additional topics included the feasibility of placing gas tanks near Building 920, the installation of the tent, and the minimal works needed in buildings B911, B918, B920, and ECN3. 

From the presentation and the discussions, the following actions were defined: