Past week: In beam to LA1 (PAC)
- Setup in advance, and checked a day before the run.
- Smooth operation for 1 day of In to LA1.
Current week : In beam to IDS
- Checks will be perforned after this meeting. Start of the run tomorrow.
Coming week(s): LIST for Collaps (Tm) then In-source spectroscopy (Pm)
- Laser preparation ongoing for both Tm and Pm ongoing.
- Installation of the controls in the HRS HV cage will be done tommorrow at 13:30.
- LIST target will be put on the HRS FE on Friday.